A phased construction plan breaks a renovation into defined zones or stages, so each finished area can be handed back and used while work continues in the rest of the building. In Metro Vancouver, it is the document that lets a retail centre, office floor or warehouse keep operating, and the one a building permit reviewer, landlord and fire department will all expect to see. We build these plans around the constraints of the building first and the construction logic second.
TL;DR
- A phasing plan is drawings plus a short narrative: phase boundaries, order of work, temporary conditions and what must be inspected before a phase is handed back.
- Phase lines should follow fire-rated walls, stair towers and mechanical zones, and be set only after operating hours, lease terms and landlord rules are written down.
- In Vancouver, an occupied part of a building under construction must be separated from the work area by a fire separation of at least one hour, and fire protection systems must stay operational.
- Every phase needs its own scope, budget and closeout, because each phase can bring a fresh mobilization of trades and slower productivity than an empty building.
- Review the schedule weekly and keep a two-week look-ahead, so deliveries, shutdowns and inspections never surprise tenants.
Table of Contents
- What a phased construction plan is
- What the plan must contain
- Set the phase lines from constraints, not from the trades
- What the BC Building Code and the City of Vancouver require
- Landlord rules and working hours in Vancouver buildings
- Budgeting a phased job
- Scheduling, communication and adjustment
- How phasing looks on different Metro Vancouver projects
- Working with Multigroup on a phased project
- Our perspective
- FAQ
- Sources
What a phased construction plan is
A phased construction plan divides one project into planned stages, usually by zone, floor, tenant suite or time period, and sets the order, boundaries and turnover conditions of each stage. It is not the same as the generic phases of a project, such as design, permitting, construction and closeout.
The distinction matters when you brief a contractor. The standard sequence of a building project (site preparation, structure, building enclosure, mechanical and electrical rough-in, finishes, commissioning) describes the type of work. A phasing plan decides where and when each part of the building is worked on and given back. One glossary definition describes phasing as dividing work into planned stages to coordinate access, occupancy, approvals, shutdowns or turnover.
Phasing is also different from sequencing. Sequencing is the activity-by-activity order that a site superintendent uses day to day. Phasing groups that work into large blocks driven by budget, occupancy or site logistics, which is the level owners and property managers work at.
Not every job needs it. A vacant unit with a single tenant improvement can run as one continuous job. Phasing earns its cost when part of the building must stay open: a café that trades through a renovation, a medical clinic renovating one wing at a time, a multi-tenant office upgrading corridors while tenants keep trading, or a warehouse that cannot stop shipping.
What the plan must contain
A usable phasing plan answers 40 to 60 words of practical questions before work starts: where each phase begins and ends, what is included, how occupants are separated from the work, and what must pass inspection before the next phase starts. Anything left to a narrative alone tends to be rediscovered by trades after award.
For a commercial building in Metro Vancouver, we expect the plan to cover these items:
- Phase boundaries on drawings. Each zone is shown with its limits, not described in a paragraph.
- Scope per phase. Included work, exclusions, permits, responsibilities and the standard that counts as complete.
- Schedule and dependencies. Milestones for each phase, plus what depends on what, such as a ceiling cannot close until sprinkler and alarm work is inspected.
- Exit criteria. The inspections, approvals and commissioning needed before an area is released to occupants.
- Separation of occupants from construction. Barriers, dust control, noise control and ventilation isolation.
- Access and egress. Separate routes for workers, deliveries, customers and staff, with exits kept clear and signed.
- Fire and life safety. How sprinklers, alarms and egress lighting stay in service, or are replaced in stages.
- Utility shutdowns and temporary services. Planned outages with notice periods and who approves them.
- Closeout per phase. Deficiency lists, turnover documents and demobilization before the next zone is opened.
The University of Minnesota’s procedures for phased construction are a useful illustration of the logic, even though they apply in the United States: sprinkler and alarm systems must be complete and functional and overlap between phases where needed, and the exit system must work throughout. They also note that phase locations tend to follow mechanical systems or logical dividers, because partly finished areas have to be balanced. The same thinking applies under the BC Building Code.
Each phase should end at a stable point. The area is safe, weatherproof where relevant, and usable, and any temporary work needed to get there has been identified and priced. A phase that finishes mid-way, with open ceilings and live services unprotected, is not a handover; it is a hazard.
Set the phase lines from constraints, not from the trades
The best phase lines come from how the building operates. Write down operating hours, peak trading seasons, staff and customer counts, loading dock schedules, lease obligations and permit conditions first, then draw lines along natural boundaries such as fire-rated walls, stair towers and mechanical zones.
A common mistake is to let the trades choose. An electrician would prefer to work floor by floor; a restaurant would rather close the dining room for a stretch than take the kitchen offline. The operator’s cost of downtime is usually larger than the contractor’s cost of an extra mobilization, so it should drive the plan.
A practical way to start is with an operations map rather than a calendar:
- Which routes must stay open for customers, staff and deliveries?
- Which periods are blackout periods, such as a retail holiday season, month-end for an office tenant, or a clinic’s busiest clinic days?
- Which systems cannot go down at all (refrigeration, server rooms, medical gas, fire alarm)?
- What air-quality, odour and security expectations apply?
Once those answers exist, scheduling becomes a planning exercise instead of a negotiation. For the wider case for doing this work before anyone mobilizes, see our piece on why pre-construction planning saves time and money.
What the BC Building Code and the City of Vancouver require
In Vancouver, an occupied portion of a building under construction must be separated from the construction area by a fire separation rated at no less than one hour, and fire protection systems must remain operational unless shutdown protection meets the Fire By-law. These rules shape where you can draw a phase line and how long a system can be offline.
The Vancouver Building By-law 2019, Division B, Section 8.2 sets out three requirements that matter for phasing:
- Where part of a building under construction is occupied, the occupied part is separated from the construction part by a fire separation with a fire-resistance rating of at least one hour.
- Fire protection systems stay operational throughout the building during construction, unless shutdown protection complies with the Fire By-law.
- Where a partly occupied building is undergoing deconstruction or demolition without an active fire alarm system, a fire watch with inspections at least hourly is required.
The permit side has its own checkpoints. The City’s Tenant Improvement Review Checklist calls for a building permit before construction, a contact list naming the prime contractor responsible for construction safety, submission of the construction schedule to the Fire Department, and City approval of WorkSafeBC procedures before hazardous-material abatement. Our tenant improvement guide to Vancouver permits walks through that sequence in more detail.
If you want to occupy part of the building before the whole project is finished, the process is stricter. Under the BC Guide to the Letters of Assurance, phased occupancy under a single building permit is allowed only where the segment is clearly defined in the professional schedules, substantially complies with the BC Building Code and the submitted drawings, has complete integrity for fire and life safety, and the excluded segments are clearly protected from premature use. Final schedules covering the entire project are still required before the final occupancy permit.
On projects using the City’s Certified Professional Program, the program guide states that for partial occupancy the Certified Professional coordinates an occupancy protocol with a construction safety plan, reviewed and accepted by the Chief Building Official, and the contractor submits a site-specific Fire Safety Plan for the occupied portions to the Fire Department.
In practical terms: decide early whether you will need partial occupancy, because it changes who has to sign what, and when. The permit authority, the registered professionals and the prime contractor all need to see the same phase boundaries. Under WorkSafeBC rules, someone must be the prime contractor for the site; we cover those duties as part of managing the project.
Landlord rules and working hours in Vancouver buildings
Most multi-tenant buildings in Vancouver add their own rules on top of the code: restricted hours for noisy work, insurance minimums, permit and WorkSafeBC paperwork, and protection of common areas. A phasing plan has to be written to those rules, or the schedule will not survive its first week.
Three published examples show the range:
- At QuadReal’s Broadway Tech Centre, the tenant construction guidelines (November 2021) require a City of Vancouver building permit, a WorkSafeBC clearance letter, and at least $5,000,000 in occurrence liability insurance naming the landlord as additional insured. Coring, drilling and other noisy work is kept outside 7:00 am to 6:00 pm Monday to Friday and 7:00 am to 1:00 pm Saturday.
- At Park Place on Burrard Street, the tenant design criteria (January 2021) move core drilling, hammer drilling, table saws and other noisy, dusty or vibratory work to between 6:00 pm and 6:00 am on weekdays, or weekends, with the landlord’s advance approval. Odour-generating work also moves to after-hours or weekends.
- A contractor procedures pamphlet for a City of Vancouver-owned building (2010) calls for hoarding or plastic sheeting to protect common areas and other tenants from dust, mechanical system shutdown during demolition, proof of insurance and WCB for every contractor, and no disconnecting of fire alarm panels without Building Management approval.
These are documents from specific buildings, and each landlord’s current manual governs its own site. The lesson for a property manager is consistent: get the building’s contractor rules into the phasing plan before pricing, because after-hours work changes crew cost, and the hours can decide which scope belongs in which phase. Loud demolition and anchoring typically go in the first window of each zone, while quieter finishing work can run during the day.
Our article on keeping your business open during a Metro Vancouver commercial renovation covers the tenant-facing side of this in more depth.
Budgeting a phased job
A phased project costs differently from a continuous one, and the estimate has to show it. Each phase can mean its own mobilization for trades, and crews inside an occupied building rarely work at the rate they would in an empty shell. A budget that prices the work as one continuous job will miss both.
When you review a bid, check for these items:
- Mobilization per phase. A renovation split into four phases may bring a trade back four times. Ask for it to be shown, not buried.
- Temporary protection. Barriers, fire-rated separations, negative air or dust control, and temporary signage and wayfinding, priced per phase.
- After-hours premiums. Where the landlord or tenant requires night or weekend work, labour costs rise, so the plan should identify which tasks truly need those windows.
- Temporary services. Power, lighting, egress and fire protection that has to be kept running or replaced during each stage.
- Per-phase closeout. Deficiency lists, inspection requests and cleaning before handover.
All amounts should be in Canadian dollars, with a clear split between base scope and phasing costs, so you can see what a different phase layout would change. Each phase should also have a clear start and end, a payment schedule and a completion standard, so that approvals and payments follow the physical handover rather than a calendar date.
One caution on costs we see owners underestimate: a phase plan that ignores utility and life-safety dependencies. If the sprinkler zone covers two phases, you cannot finish and release the first without addressing the second. Catching that on the drawings costs nothing; catching it after award costs a change order.
Scheduling, communication and adjustment
A phasing plan is a living document. Use three layers of schedule: a plain-language milestone schedule from approvals to closeout, a phase schedule showing what happens in each zone and when handovers occur, and a two-week look-ahead that lines up deliveries, shutdowns, inspections and daily controls.
The look-ahead is the early-warning system. If next Tuesday’s water shutdown has not been confirmed with the tenants on that floor by the preceding Wednesday, the schedule is already at risk. Our construction scheduling checklist lists the items we track.
Good project governance for a baseline schedule looks the same across jurisdictions. The City of Markham’s Field Services Manual (November 2025), for example, uses a baseline construction schedule reviewed at regular progress meetings, with minutes circulated, and the schedule is used to monitor progress, take corrective action and communicate status to stakeholders. The principle carries over to a tenant improvement or occupied commercial project: one baseline, regular meetings, written minutes.
For an occupied building, we recommend this rhythm:
- Before each phase starts: confirm boundaries, barriers, exits and any shutdowns in writing with the property manager and affected tenants.
- Daily: a short update covering what was completed, what is next, expected impacts such as noise or odour, open issues and who to call.
- Weekly: a progress meeting with the owner’s representative, the contractor and any consultants, with minutes.
- At each handover: a walk-through, deficiency list and written acceptance of the area before occupants return.
- Whenever conditions change: revise the phasing document, date the revision and record who received it.
Unknown conditions behind existing walls and ceilings are the most common reason a phase runs long. Build a short contingency window between phases for that reason, rather than stacking phases back to back.
How phasing looks on different Metro Vancouver projects
The same principles produce different plans depending on the building. The phase line follows the operation: what has to keep running decides where the work can start.
Multi-tenant office and retail. Phases usually follow suites or floors, with common corridors and elevator lobbies protected. The landlord’s hours and hoarding rules often set the plan. See our tenant improvements and retail buildouts pages.
Restaurants and cafés. The kitchen and the dining room are different phases because they have different downtime costs and different inspection requirements. Where a business trades through the work, the sequence is chosen to protect the revenue-producing area for as long as possible. Our coffee shop and restaurant renovation page covers the project type.
Warehouses and industrial. Zones are typically defined by racking aisles, dock doors and mechanical systems. Shipping schedules and forklift routes decide the sequence. See warehouse renovations.

Across all three, the common thread is that the owner decides what cannot stop, and the contractor builds the sequence around it.
Working with Multigroup on a phased project
If your building has to stay open, the plan and the contractor need to be chosen together. Multigroup Contracting is a Vancouver commercial general contractor that delivers tenant improvements, retail and restaurant buildouts, office fit-outs, warehouse renovations across Metro Vancouver. We manage City of Vancouver and municipal permits, BC Building Code compliance, WorkSafeBC prime contractor duties, and phased or after-hours work in occupied buildings.
We deliver the work as a general contractor or through construction management, are WorkSafeBC registered and carry $5M in liability insurance, and build our approach around property managers and operators who need clear scope, clear schedules and one accountable contractor. To scope a phased project, start with our commercial construction services or Get a free quote.

Bring the building’s contractor manual, any lease restrictions and your operating calendar, and we can turn them into phase boundaries and a schedule that fits.
Our perspective
Most phasing problems are decided before a shovel or a screwdriver moves. They come from a plan that lives in a narrative, a schedule that assumes full productivity in an occupied building, or a budget that treats four phases as one job.
We prefer to start with what the building cannot give up: the exits, the fire alarm, the loading dock, the till, the corridor a tenant uses every day. Those answers set the phase lines. Then we price each phase on its own, so the owner can see what a different layout would change.
Because we deliver the work as a general contractor or through construction management, one accountable contractor handles the permits, the WorkSafeBC prime contractor duties and the day-to-day coordination with tenants. That is what lets a property manager hand over a phase when that phase’s closeout is complete, and keep the next one on track.
Multigroup Team
FAQ
What is the difference between construction phasing and construction sequencing?
Phasing groups work into major stages of a project, driven by budget, occupancy or site logistics, and it is the level owners and property managers plan at. Sequencing is the order of individual tasks within those stages, used by the site team daily. A good plan has both, and the phase plan comes first.
Does a phased renovation need more than one building permit in Vancouver?
Not necessarily. Under the BC Letters of Assurance guide, phased occupancy can be handled under a single building permit if each segment is clearly defined, complies with the Building Code and is safe on its own. Your project team and the City’s permit staff should confirm the approach for your building before work starts.
Can work be done after hours in a multi-tenant building?
Often yes, and in many Vancouver buildings noisy work is required to be done after hours. The hours differ by landlord, so check the building’s contractor or tenant construction manual and get approval for each window in advance. Plan the schedule around those windows from the outset.
Does phasing increase the cost of a renovation?
It usually changes the cost structure. Phasing adds mobilizations, temporary protection and per-phase closeout, and occupied-building work can be slower than work in an empty space. It also protects the revenue or operations that would otherwise stop. Ask for phasing costs to be itemized in the estimate.
Who should be involved in writing the phasing plan?
The owner or property manager, the contractor, the design team and, where required, the authority having jurisdiction. Tenants and the landlord’s building management should see the plan before it is final, particularly where access, noise or shutdowns affect them.
Sources
- Vancouver Building By-law 2019, Division B, Section 8.2
- City of Vancouver Tenant Improvement Review Checklist
- Guide to the Letters of Assurance (BC)
- City of Vancouver Guide to the Certified Professional Program
- Broadway Tech Centre tenant construction guidelines
- Park Place tenant design criteria manual
- Contractor procedures and guidelines pamphlet
- Procedures for Phased Construction Projects, University of Minnesota
- City of Markham Field Services Manual
- Commercial Construction Glossary: Key Terms