A strata hallway renovation in Vancouver is a common property project. It needs an owner vote in most cases, a signed letter from the strata to the City, a building permit, and a contractor who works around residents who live in the building every day. Get the sequence right and the work is predictable. Get it wrong and it stalls at the permit counter or the general meeting.
This guide is written for strata councils, property managers and building owners in Metro Vancouver. It covers how the project is scoped, approved, permitted under the BC Building Code process, budgeted in CAD and sequenced in an occupied building, and what you should expect from the general contractor you hire.
TL;DR
- Hallways are common property. Significant changes to them typically need a 3/4 vote at a general meeting, unless the work is an emergency to prevent significant loss or damage.
- The City of Vancouver requires written strata approval, signed by the council chair, before it issues a permit for work on common property such as corridors.
- If the strata hires several trades directly, it can end up holding prime contractor duties under WorkSafeBC. One general contractor taking that role removes the risk from the council.
- Check fire separations, exits and hazardous materials before demolition. Surprises found mid-project are the usual cause of change orders.
- Fund the work through the contingency reserve fund or a special levy, and explain the funding model to owners well before the vote.
Table of Contents
- What a hallway renovation actually covers
- Approvals: the owner vote and how it is funded
- The City of Vancouver permit and the strata letter
- Who carries the safety duties: WorkSafeBC and the prime contractor
- Life safety checks before demolition
- Scheduling work in an occupied building
- Budgeting a hallway renovation in CAD
- Our perspective: what we see on strata corridor projects
- Working with Multigroup on your strata corridor project
- FAQ
- Sources
What a hallway renovation actually covers
A strata hallway renovation is any upgrade to shared corridors, landings and entry foyers: flooring, wall finishes, ceilings, lighting, unit door frames, signage and sometimes mailrooms or elevator lobbies. The scope sets the approvals, the permit route and the schedule, so define it first and in writing.
Most projects land in one of three tiers:
- Refresh. Paint, new wall protection, signage and minor repairs. Often no permit if nothing structural, fire-rated or electrical changes, but confirm with the City before assuming.
- Standard renovation. New flooring, wall finishes, ceiling and lighting replacement. This is the typical project, and it usually needs a building permit and an electrical permit.
- Upgrade with code work. Changes to fire separations, exit paths, sprinkler heads, fire alarm devices or accessibility. These involve design professionals and a more detailed permit application.
A fixed scope matters more than any other document. A scope that lists the corridors by floor, the finishes by room, and the exclusions (for example, unit entry doors owned by individual owners) is what lets a contractor give a firm price and lets owners see what they are voting on.
Approvals: the owner vote and how it is funded
In B.C., significant changes to the appearance or use of common property typically need a 3/4 vote at a general meeting. The exception is work needed to prevent significant loss or damage or to ensure safety, which can proceed without a prior vote. Funding is the second approval: owners need to know who pays and how.
The Province explains that a special levy must be approved by owners at a general meeting, and the same page covers the 3/4 threshold for significant common property changes and the emergency exception. The Province also lists the four types of strata votes: majority, 3/4, 80% and unanimous. Your strata bylaws and legal advice decide which applies to your specific project, so confirm with your strata lawyer where the scope is borderline.
A clean hallway refresh may be funded from the operating budget. A full renovation usually comes from the contingency reserve fund (CRF) or a special levy. The Province notes that all stratas with five or more lots must obtain depreciation reports. That report is the best planning tool you have: it shows when corridor finishes reach the end of their expected life and what the CRF should hold, so the renovation is planned spending rather than a surprise levy.
Property managers tell us the same thing repeatedly: the vote is won or lost on communication. The Province distinguishes between who arranges a repair (the strata) and who pays for it (the owners). Send owners the scope, the fixed price, the funding source and the schedule before the meeting, not at it.

The City of Vancouver permit and the strata letter
The City of Vancouver will not issue a building permit for work in corridors until the strata confirms in writing that it accepts the proposal. The letter is signed by the strata council chair. Build it into the project calendar early, because it is the document that most often holds up an application.
The City’s bulletin on permits for strata buildings says written strata approval is required when proposed work involves common property, and corridors are common property. Put the letter on a regular council meeting agenda rather than waiting for the annual general meeting. A contractor who has prepared the drawings and scope can hand the council a ready-to-sign package, which keeps the meeting short.
For the application itself, the City publishes a Multi-Unit Residential Building Renovation checklist, updated March 2026, listing what a building permit submission needs for this building type. Your contractor should work through it before submission, not after the City responds with questions.
On timing, the City reports that its Permit Improvement Program has made permit processing faster, and commercial renovation permits are being issued roughly 45 percent faster than in 2022 according to the research we reviewed. That helps, but processing speed does not fix an incomplete package or a missing strata letter. Plan permit time as a real line in the schedule. For a walk-through of the paperwork, see our permitting checklist for Vancouver.
If your building is in Burnaby, Surrey, North Vancouver, Coquitlam, New Westminster or Langley, the same principle applies but each municipality has its own application process and timelines. Confirm with the local building department.

Who carries the safety duties: WorkSafeBC and the prime contractor
On any construction site, someone must be the prime contractor under WorkSafeBC rules. If a strata hires painters, flooring installers and electricians separately, the strata council can become the prime contractor by default and take on responsibility for site coordination and safety. Hiring one general contractor normally moves that duty to a professional.
This catches many councils off guard. Prime contractor duties include coordinating the safety activities of every employer on site, which is a heavy responsibility for volunteer owners. The rules sit in Part 20 of the OHS Regulation. Ask any contractor you consider to confirm in the contract that they act as prime contractor, and ask for proof of WorkSafeBC coverage and liability insurance. We carry $5M liability coverage and WorkSafeBC registration, and we take on the prime contractor role on the projects we manage.
Two other requirements to know:
- Notice of Project. WorkSafeBC requires a notice of project at least 24 hours before work begins when the combined cost of labour and materials exceeds $100,000. WorkSafeBC’s page on whether you need a notice of project explains the filing. Many full hallway renovations in mid-sized buildings cross this threshold.
- Hazardous materials survey. Before renovation or demolition, a qualified person must survey for hazardous materials such as asbestos. Older buildings often have asbestos in vinyl flooring, adhesives, textured ceilings or drywall compound.
Life safety checks before demolition
Even a cosmetic-looking corridor upgrade can trigger a fire code review if it changes fire separations or exit paths. Confirm the building’s fire separation status and the flame spread ratings of proposed finishes before demolition starts, not after an inspector flags them. This one early check prevents most stop-work orders and change orders.
The practical steps are:
- Review the original drawings and any previous permits for the corridor, to see which walls and doors are fire-rated.
- Confirm that new wall and ceiling finishes meet the flame spread requirements for exit corridors.
- Keep exits, exit signs, emergency lighting, sprinkler coverage and fire alarm devices functional and unobstructed throughout the work, and plan for temporary relocation of devices where the ceiling is opened.
- Coordinate with the building’s fire alarm contractor for any impairments, and notify residents when a system is out of service.
The Province’s guidance on handling emergencies in stratas reminds councils that equipment such as elevators, fire alarms and smoke detectors must be properly maintained. A renovation must not leave any of them compromised.
Asbestos deserves its own line in the schedule. If the survey finds it, abatement has to be completed and cleared before general work starts, and that sequence changes your timeline. Our GC playbook on avoiding asbestos abatement delays in Metro Vancouver stratas covers how to plan for it, and our note on the 48-hour notice for property managers explains the notification step.
Scheduling work in an occupied building
Residents, mail carriers, delivery drivers and emergency services all use the hallway you are renovating. The answer is to work in short, sealed zones, floor by floor or wing by wing, with clear notices, protected paths, and agreed work hours. A good schedule is built around access, not just around trades.
A typical sequence for a mid-rise corridor renovation looks like this:
| Phase | What happens | Typical considerations |
|---|---|---|
| 1. Scope and survey | Walk the building, hazardous materials survey, fire separation review | Do this before pricing is final |
| 2. Approvals | Owner vote, funding decision, strata letter | Put the letter on a council agenda early |
| 3. Permit | Application, review, permit issued | Allow the City’s review time, plus corrections |
| 4. Mobilization | Notices to residents, protection, staging area, elevator booking | Confirm move-in and move-out dates |
| 5. Work by zone | Demolition, rough-in, ceiling, walls, flooring, lighting | One zone open at a time |
| 6. Finish and inspect | Deficiency walk, final inspection, close-out | Hand over warranties and drawings to the manager |
Strata bylaws usually set permitted work hours, and many buildings restrict noisy work to weekdays during daytime hours and bar it on statutory holidays. Check your own bylaws and building rules and put them into the contract. Noisy work such as demolition and flooring prep should be grouped into short, announced windows. Loud or dusty tasks can also be scheduled for hours when fewer residents are home.
Elevators and loading areas are often the real bottleneck. Reserve the freight elevator, agree where materials stage, and protect elevator interiors and lobby floors. Our guide to keeping a building running during an occupied renovation goes deeper on sequencing, communication and protection, and the principles apply equally to stratas.
Resident communication is part of the scope. Expect to issue a notice before mobilization, a weekly look-ahead during the work, and a named contact for complaints. Property managers who send these notices consistently receive far fewer calls.
Budgeting a hallway renovation in CAD
Budget by scope, not by a per-square-foot rule of thumb. Corridor costs vary widely with building age, number of floors, fire-rated work, lighting and electrical changes, hazardous materials, and access constraints. The only reliable number is a fixed-scope quote based on a site walk-through.
We do not publish standard prices, because two corridors that look alike on paper can differ greatly once ceilings are opened. What we can tell you is what drives the number, so you can compare quotes fairly:
- Floor area and number of floors. Mobilization, protection and elevator time repeat on every floor.
- Existing conditions. Subfloor repairs, uneven walls and old adhesives add labour.
- Electrical and lighting. New fixtures, emergency lighting and controls need an electrical permit and may need panel work.
- Fire and life safety. Relocating or re-protecting devices, doors and ratings.
- Hazardous materials. Survey costs, and abatement if found.
- Working conditions. Restricted hours, phased zones and after-hours work extend the schedule and the labour hours.
- Soft costs. Permit fees, design or engineering where needed, and the WorkSafeBC notice and site safety plan.
Add a contingency line to the approved budget for conditions found once walls are open. Owners are far more comfortable voting on a figure that already includes it than approving a surprise top-up later. If the levy is based on a quote, make sure the quote’s validity period covers the date the vote and the permit are realistically expected.
When you compare bids, check that each one covers the same scope, exclusions, work hours, permit responsibility, prime contractor role, insurance and warranty. The cheapest bid that leaves out the permit and the prime contractor duties is usually not the cheapest project.
Our perspective: what we see on strata corridor projects
We are a commercial general contractor in Vancouver, and strata and multi-family common area work is a core part of what we deliver, alongside tenant improvements, retail and restaurant buildouts and warehouse renovations. The projects that run well share a few traits, and none of them is about finishes.
First, the scope is fixed before the vote. When owners see a clear scope, a firm price and a schedule, the 3/4 vote is far easier to win, and the project is far less likely to be reopened at the next general meeting.
Second, the strata letter and the permit are treated as schedule items, not afterthoughts. We prepare the package so the council can sign it at an ordinary meeting.
Third, one accountable contractor beats a collection of trades. We self-perform and manage the whole project, take on the prime contractor role, handle the permits and code compliance, and run phased or after-hours work so the building keeps functioning. The council gets one point of contact instead of coordinating five.
Fourth, early surveys save money. Checking fire separations and hazardous materials before demolition is cheap. Finding them after is not.
— MultigroupTeam
Working with Multigroup on your strata corridor project
We help strata councils and property managers across Metro Vancouver plan and deliver hallway and common area renovations: scope definition, permit management, WorkSafeBC prime contractor duties and phased work in occupied buildings. We are licensed, insured with $5M liability coverage, and built around clients who need fixed scope and clear schedules.
You can see how we approach this type of work on our commercial renovation services page, and our portfolio shows completed projects. If you are preparing for a council meeting or a general meeting, send us the building address and the corridors involved and we will walk the site with you. Contact us to book it.
FAQ
Does a strata hallway renovation need a vote of the owners?
Usually, yes. Significant changes to the appearance or use of common property typically need a 3/4 vote at a general meeting. Urgent work to prevent significant loss or damage, or to ensure safety, can proceed without a prior vote. Check your bylaws and ask your strata lawyer if your scope sits between the two.
Do we need a building permit to renovate a strata corridor in Vancouver?
Many corridor renovations do, particularly when work touches fire separations, exits, electrical or ceilings. Because corridors are common property, the City requires written approval from the strata before issuing a permit. Your contractor should confirm the permit requirement with the City for your scope before pricing.
Who is responsible for site safety if the strata hires trades directly?
If the strata hires several contractors itself, the council can end up as the prime contractor under WorkSafeBC rules, with responsibility for coordinating site safety. Hiring a single general contractor who agrees in writing to act as prime contractor normally moves that responsibility to the contractor. Confirm this in the contract.
How should a strata pay for a hallway renovation?
Small refreshes may come from the operating budget. Larger projects are typically funded from the contingency reserve fund or a special levy approved by owners. A current depreciation report helps you show owners when the work is due and how it should be funded.
Can the building stay occupied during the work?
Yes. Corridor work is routinely done with residents living in the building, using sealed work zones, protected routes, set work hours and regular notices. Exits, fire alarms and emergency lighting must stay functional throughout.
Sources
- Special levies in stratas, Province of British Columbia
- Types of strata voting, Province of British Columbia
- Strata depreciation report requirements, Province of British Columbia
- Paying for repair and maintenance, Province of British Columbia
- Handling emergencies in strata corporations, Province of British Columbia
- Permits for strata buildings, City of Vancouver
- Multi-Unit Residential Building Renovation Application Checklist, City of Vancouver
- Permit Improvement Program, City of Vancouver
- OHS Regulation Part 20, WorkSafeBC
- Notice of project resources, WorkSafeBC