As-built drawings, often called record drawings, are the official record of what was actually built, and they are a required closeout deliverable. The contractor keeps red-line markups during construction, then delivers digitized, signed or stamped files where required. You need them for final handover, occupancy and every future renovation or maintenance call.


TL;DR:

  • The contractor remains accountable for accuracy even when consultants review the set, so contracts should assign trade markups, review, and owner acceptance clearly.
  • Municipalities may require dimensioned, scaled digital drawings before final inspection or occupancy, and missing records can delay permits, handover, or final payment.
  • Require native DWG files or project BIM models, matching PDFs at 100% scale, revision history, and required seals; handwritten markups alone are not enough.
  • Trades should update a live field markup set as changes happen, then transfer it into CAD or BIM and verify the files before ceilings close.
  • Before acceptance, compare disciplines at shared locations, confirm manuals and signatures are included, and check three or four building locations against the drawings.

Multigroup
Keep Commercial Handover on Track
Multigroup manages commercial fit-outs and municipal permits across Metro Vancouver, helping owners coordinate project requirements before occupancy.
Visit Multigroup

Table of Contents

What are as-built drawings, and how do they differ from design and shop drawings?

As-built drawings are official records of the conditions of a facility as constructed. They show the precise location, size and configuration of structural, mechanical, electrical and plumbing elements. They also record every deviation from the original plans, including change orders, site-specific adjustments and material substitutions.

The terminology matters. The B.C. Ministry of Transportation has moved from “as-built” to “record drawings” to stress that the final document must be authoritative and verified, not just a contractor’s markup. For your closeout, treat the two terms as the same deliverable, with “record” signalling that someone has checked it.

Shop drawings are a different animal. They are submitted in a specified format, stamped where required, and coordinated with the contract documents before fabrication or installation. They show how a trade intends to build something. Record drawings show what actually went in. Design drawings show what was planned. Only the last one tells your facilities team where the pipe really runs.

Design, shop, and record drawing differences

Who prepares as-built drawings and who is responsible?

The contractor owns the record. That responsibility does not move to the consultant, even when a consultant reviews the submission. Contractors remain responsible for the accuracy of as-built drawings, and consultant review does not relieve them of it. In practice, responsibility splits like this:

  • General contractor: keeps the live red-line set on site and delivers the final digital files.
  • Subcontractors: mark up their own trade work as it is installed and hand it to the GC promptly.
  • Consultants: review the submission for consistency with design intent and apply seals where required.
  • Owner or property manager: states the deliverable requirements in the contract and accepts or rejects the submission.

The contract anchors all of this. CCDC project closeout guidance lists as-built or record drawings among the required closeout submittals. Under the CCDC 2-2020 changes, some provisions moved into Division 01, and a copy of the as-built drawings completed to date must be available on site.

When are as-built drawings required?

Record drawings come due at the end of the job, but the groundwork starts on day one. The usual trigger points are substantial performance, final inspection, handover and occupancy. Under municipal bylaws, providing as-built drawings can be a condition for issuing a final inspection notice or occupancy permit. Skip them and your tenant may not get the keys.

Here is what to expect at each stage:

  • Final inspection: the building department may ask for the record set before signing off.
  • Municipal submissions: checklists commonly demand fully dimensioned plans to scale and digital-only submissions, so confirm local format rules early.
  • Punchlist and handover: the final set should be submitted alongside deficiency closeout, not weeks later.
  • Ongoing site records: contract documents, change orders and record documents must be kept at the place of work and be available for review.

Incomplete records stall closeout. A missing set can hold up occupancy, delay final payment releases and leave you paying for investigative work later.

What should the deliverables include?

Ask for specific files, not a vague promise of “drawings.” The standard expectation is AutoCAD (.dwg) or PDF at 100% scale, and handwritten field notes alone are not acceptable for final submission. Large owner organisations go further, requiring complete sets across architectural, structural, mechanical, electrical, plumbing and fire protection, delivered digitally.

A solid closeout requirement list looks like this:

  1. Native AutoCAD DWG files for every discipline, or BIM models where the project used them.
  2. PDF sets at 100% scale matching the DWG files.
  3. Registered point clouds where laser scanning was used.
  4. Seals and signatures where the building code or contract requires them. The BC Building Code’s administration provisions cover required drawing information, including signatures and professional seals.
  5. A revision history and consistent titleblocks and layering.
  6. Hard-copy sets only if your organisation asks for them.

Pro Tip: Put the file formats, scale and layering standard in the contract before work starts. Fixing a CAD standard dispute at closeout costs far more than stating it in the tender.

How are as-built drawings produced?

Good record drawings are built continuously, not reconstructed. Maintaining a live set of red-lines on site throughout the project matters because neglecting it often forces an inaccurate reconstruction right before occupancy applications. The field set is the source of truth, and everything downstream depends on it.

The workflow typically runs in these steps:

  • Live red-lines: each trade marks changes the day they happen, and the superintendent checks the set during site walks.
  • Scanning where it pays off: for complex mechanical, electrical and plumbing coordination or tight existing conditions, laser scanning captures what is behind the finishes before ceilings close.
  • Transfer to CAD or BIM: the red-lines or point cloud become clean DWG or model files. Professional standards require as-built drawings to be updated in CAD format so they stay usable for future renovations and operations.
  • QA/QC and sign-off: a reviewer compares the new files against the red-lines, then the set is signed or stamped where required and submitted.

Hand-marked prints alone are a gamble. Building departments and future facility managers may reject them, and failing to digitize often delays closeout.

How do good as-built records pay off after closeout?

Accurate records save money the next time anyone opens a wall. The first payoff is less rework. A designer planning a retrofit works from verified conditions instead of guesses, so fewer surprises reach the field and fewer change orders follow.

The second is faster planning. Prefabrication and fit-up depend on knowing real dimensions, and facilities teams use the same records for operations and maintenance. As-built records document the exact configuration of structural, mechanical, electrical and plumbing elements, which is precisely what a maintenance crew needs when a valve has to be found fast.

The third is system fit. If you manage a portfolio, require deliverables that match your asset-management system. Owners with large portfolios already specify the file types and submission channels, as the ARES drawing guidelines show. Our related piece on permit versus construction drawings helps you see where each set fits.

What should you check before accepting the drawings?

Accept the set against a written checklist, not a feeling. Work through these items in order:

  1. Native CAD or BIM files and 100% scale PDFs are all present, with revision history.
  2. Operations and maintenance manuals and certified system documentation are included. Closeout submittals commonly package these with record documents for owner handover.
  3. Stamps or signatures are on the sheets where required.
  4. Architectural, structural and mechanical, electrical and plumbing sheets agree with each other at shared locations.
  5. A reviewer has documented sign-off, and the files are stored where your team can find them.

Pro Tip: Spot-check three or four locations in the building against the drawings before you sign. If a ceiling-space measurement is off, you can spot-check the set’s accuracy. For help catching conflicts between specifications and drawings, ArosBid’s guidance on spec versus drawing conflicts is a useful reference.

How do we manage red-lines and deliver permit-ready record drawings?

We treat the record set as a project deliverable from the start of the project. On tenant improvements, retail buildouts and warehouse renovations, our superintendents keep the red-line set current as work proceeds, and we review it against what is actually installed before ceilings and walls close up.

Redline plan beside exposed commercial ceiling services

At the end of the job, we coordinate the closeout with the permit documents we managed along the way. You can set expectations in the contract: formats, red-line update frequency and sign-off. Our guide to must-have construction documents lists what else belongs in your closeout package, and our overview of post-construction service covers the handover that follows.

What most owners get wrong about closeout drawings

Most owners treat as-built drawings as paperwork to chase at the end. That is the mistake. By closeout, the only thing left to do is copy what was recorded, and a record that was never kept cannot be recovered. The work that decides quality happens months earlier, in the field, when a trade moves a duct and someone either records the change or does not.

So put your attention where it counts. First, write the deliverable requirements into the contract. Second, ask to see the red-line set during construction, not at the end. Third, hold back final acceptance until you have spot-checked the files against the building.

The usual advice, to “get the drawings at closeout,” is too late to help. Another common habit, accepting a PDF scan of marked-up prints, feels like progress but fails the first time a designer needs editable files. Insist on native CAD or BIM, and you save your next project a survey.

— MultigroupTeam

How can we help with compliant as-built drawings on your commercial project?

If you want record drawings that hold up at occupancy and after, we build that into the scope from the start. We deliver office renovations and tenant improvements across Metro Vancouver, retail buildouts and warehouse renovations, with permit coordination. In your proposal request, ask for the red-line update schedule and the stamp or sign-off process. Contact us to talk through the closeout deliverables for your project.

Multigroup

FAQ

What is the difference between a shop drawing and an as-built drawing?

A shop drawing shows how a trade plans to fabricate or install something, and it is submitted for review before work begins. An as-built drawing records what was actually built. Shop drawings and as-built drawings serve different purposes in project documentation.

How do you make an as-built drawing?

Keep a live set of red-line markups on site, updating it as changes occur. Then transfer those marks into CAD or BIM files, check them and sign or stamp them where required. Handwritten field notes alone are not acceptable for final submission.

What is the difference between as-built and construction drawings?

Construction drawings show the design intent used to build the project. As-built drawings show the finished result, including every deviation. They document change orders, site adjustments and material substitutions that the original set never captured.

Are as-built drawings the same as record drawings?

In practice, yes. Many agencies now prefer “record drawings” to signal that the document is verified and authoritative. The B.C. Ministry of Transportation circular explains the shift in terminology.

Sources

Name them in your contract so nobody argues about format later. Three layers apply: provincial guidance, CCDC contract terms and municipal rules.

On the provincial side, the B.C. Ministry’s technical circular on record drawings explains the shift to “record drawings” and the submission expectations behind it. It is a ministry document, but it shows where industry practice is heading.

On the contract side, CCDC closeout submittals include record drawings and operations manuals, as the CCDC closeout guidance describes. The CCDC 2-2020 update also requires as-built drawings completed to date to be available on site.

On the municipal side, the City of Vancouver publishes as-built drawing standards listing required content and format. Check your own municipality’s list before you finalize the deliverable schedule.