Intumescent paint is a thin coating that swells in a fire and suits exposed steel you want to keep visible. Spray fireproofing, usually cementitious, is a thick, rough-textured layer that costs less per square foot and suits concealed steel and large areas. Many commercial projects in Metro Vancouver use both. The right choice depends on what the steel looks like, the required rating, and how much of the building is occupied while work is under way.

Multigroup
Plan Commercial Fit-Out Work
Explore Multigroup’s commercial contracting work in Metro Vancouver, including tenant improvements, fit-outs, renovations, and permit management.

TL;DR

  • Intumescent coatings go on at roughly 1 to 3 mm and keep exposed steel looking like steel. Cementitious spray is thicker and rougher, and it is best hidden above ceilings or behind walls.
  • Spray systems generally cost less per square foot. Intumescent cost climbs with the fire rating and drops per unit as the scope grows.
  • In Canada, the system must carry a ULC or cUL listed design, or be tested to ULC S101, and the application has to follow that listing exactly.
  • One structural member can carry both systems, and many buildings use spray on hidden steel and intumescent on exposed steel.
  • In an occupied building, overspray, drying time, dust and access decide the schedule as much as the product does.

Table of Contents

What each system is and how it protects steel

Both systems do the same job: they slow heat so structural steel stays below the temperature at which it loses strength. They do it differently. Intumescent paint reacts and grows when heated, while spray fireproofing is a thick insulating layer already in place on the steel from day one.

Intumescent paint

The Canadian Institute of Steel Construction describes thin-film intumescent coatings as paint-like materials applied to structural steel at about 1 to 3 mm. When heated, they turn into a meringue-like insulating ash roughly 50 to 100 mm or more thick. UL reports that these coatings expand approximately 15 to 30 times their original size in standard fire tests, forming insulation that helps the steel keep its load-bearing capacity.

Intumescent coating thickness and expansion measurements

Spray-applied fireproofing

Spray-applied fireproofing is commonly called Sprayed Fire-Resistive Material, or SFRM. UL describes it as a mixture of binders such as cement or gypsum with lightweight aggregates, sprayed onto structural steel to form a thick, insulating barrier. Because it is mineral-based and does not react in a fire, it relies on thickness for its rating.

When people ask about “cementitious fireproofing”, they mean this family of products. Intumescent coatings come in water-based and solvent-based versions. A water-based, low-VOC product such as Hilti’s Fire Finish 60+ is marketed for faster installation and drying, which matters when other trades are close by.

Intumescent vs cementitious: the comparison that matters

The practical differences are finish, thickness, durability, and cost. Intumescent coatings give a smooth, paint-like surface and are thin. Cementitious spray is thick, textured and cheaper to apply across large areas. The table sets out the points a property manager or tenant usually weighs before choosing.

Factor Intumescent paint Spray (cementitious) fireproofing
Thickness About 1 to 3 mm as applied Much thicker, built up to meet the rating
Finish Smooth, paint-like, can be topcoated Rough, textured, usually hidden
Best for Exposed steel, visible features, retrofits Concealed steel, parking structures, large areas, decks
Handling Durable and well adhered Easier to damage in high-traffic areas
Complex details Needs careful coverage Efficient around bolts and connections
Cost Higher, and rises with the rating Lower per square foot

CISC lists the main advantages of intumescent coatings over SFRM as lower weight per protected surface area, durability, better aesthetic acceptance for exposed steel and good adhesion. NIST notes that spray-applied fireproofing is efficient on complex details such as bolts and connections, but it is generally easier to damage than intumescent coatings and needs careful handling in vulnerable, high-traffic areas.

SFRM is also graded by density. High-density products offer greater durability and moisture resistance at a significantly higher cost, so the cheapest spray is not always the right one for a loading area or a parkade.

Where each system fits in a commercial fit-out

Use intumescent paint where steel is part of the design and spray where steel is out of sight. A café with exposed columns or a retail unit with visible beams calls for a coating. A warehouse mezzanine frame or a parkade deck usually suits spray. The mix of uses in your building decides the rest.

Exposed steel in cafés, retail and offices

Intumescent coatings suit exposed structural steel, aesthetic projects and retrofits, and let steel features stay visible rather than being boxed in with cladding or drywall. For exterior steel on commercial buildings, exterior-grade systems are available using a rated ULC or UL system with an approved topcoat.

This is the common situation in a heritage conversion or a coffee shop renovation where the landlord’s steel columns are part of the room. Boxing them in would shrink the floor area and hide the character the tenant is paying for. In a retail buildout, the same logic applies to storefront steel and feature stair framing.

Concealed steel, large areas and industrial space

Spray fireproofing suits large coverage areas such as parking garages, structural steel and concrete decks. In warehouse renovations, a new mezzanine or a change of use that raises the required rating often brings steel that nobody will see once the ceiling goes in. A textured, lower-cost spray is the practical answer there.

When the rating, not the look, decides

If the required rating is high, intumescent thickness and cost go up quickly. A designer may then prefer spray for hidden members and keep the coating for the few exposed ones. That hybrid approach is covered below.

Approvals and fire ratings in BC

The rating comes from the building code and the design must be proven by testing. In Canada, specifications typically call for a ULC listing or testing to ULC S101, and your fireproofing contractor applies the product exactly as the listing describes. Any shortcut can void the rated assembly.

The National Building Code and provincial codes require fire-resistance ratings to be established through testing to recognized standards, and ULC S101 is the standard most relevant to structural steel fireproofing. CISC says Canadian designs using thin-film intumescent coatings apply to commercial, institutional, light-industrial and residential buildings, with listed designs appearing in ULC and cUL directories. In BC the governing document is the BC Building Code, and our BC Building Code compliance guide explains how that fits into a contractor’s scope.

Application details that affect the rating

  • Thickness and adhesion. A 2025 academic review that includes University of British Columbia researchers stresses that intumescent performance depends on precise control of application thickness and adhesion. Your contractor should record dry-film thickness readings as work proceeds.
  • Primers and substrates. SFRM can go on primed or painted steel if it passes ASTM E736 bond tests. If bond strength is poor, expanded metal lath may provide a mechanical bond. Intumescent systems must be compatible with the primer and topcoat in the listing.
  • Following the listing. SFRMs and intumescent materials should conform to the project specifications, the manufacturer’s installation procedures and minimum UL design guidelines, and improper application can compromise certification.

Fire protection does not stand alone on a commercial job. Detection and alarm systems are separate scopes that have to be commissioned alongside passive protection, and a commercial fire alarm checklist is a good prompt for the coordination questions to put to your electrical trade. Inspections on a tenant improvement are also sequenced tightly, as our piece on commercial demising wall inspections shows.

What drives the cost

Spray fireproofing generally costs less per square foot than intumescent paint, and the gap widens as the fire rating rises. Scope size also matters, because small intumescent jobs carry a heavy share of mobilization. Get a priced scope per member type rather than a single square-foot number.

AISC reports that intumescent coatings cost several times common spray-applied systems, and cost rises as the required rating increases. One US estimating source puts installed spray cementitious fireproofing at US$5 to US$14 per square foot and intumescent coatings at US$10 to US$30, depending on rating, steel complexity and access. Those are American figures in US dollars, so treat them as a ratio between the two systems, not as a Vancouver quote.

Why a small scope costs more per unit

A US selection guide shows how sensitive the price is to scope. It cites a single-column project at about US$3,400, falling to US$1,150 per column on a larger project at the same specification, because mobilization, equipment and crew-day costs are spread over more steel. It adds that cost depends on rating thickness, steel type and scope size, and that SFRM is faster for large coverage areas.

Budget questions to settle early

  1. How many members, and what rating does each need?
  2. Which steel is exposed and which is concealed?
  3. Does the steel need prep, priming or touch-up of existing coatings?
  4. What access equipment is needed, and can floors or ceilings stay open for inspection?
  5. Is the work after hours, and does that change the crew-day cost?

Our commercial construction team prices these items separately in the scope so that a change in rating on one beam does not distort the whole budget.

Using both systems on the same member

Yes, you can use both in one building, and even on one structural member. AISC notes that designs frequently use cost-effective spray-applied systems on hidden steel and intumescent coatings on the exposed portions. This is often the cheapest compliant route when part of a frame is visible.

AISC describes this as a single member or building design that can use both systems. A typical case is a beam that runs from a finished lobby into a concealed ceiling space. The finished end gets the coating, the hidden end gets spray. The same question has been asked by engineers on Hilti’s engineering forum, which is a sign this is routine rather than exotic.

The condition is that the combination must be supported by a listed design or an engineer’s acceptance, and the transition between products has to be detailed. Raise it with the consultant and the authority having jurisdiction before tender, not after the steel is coated.

Using both systems on the same member

Sequencing the work in an occupied building

In an occupied building, sequencing is often harder than choosing the product. Spray fireproofing creates overspray and dust and needs masking and protection of everything below. Intumescent coatings are cleaner but need drying time between coats. Either way, the fireproofing must be inspected before ceilings, boards and finishes close it in.

A realistic sequence for a tenant improvement with exposed and hidden steel looks like this:

  1. Confirm the rated design and the required thickness for each member with the consultant, and submit it with the permit documents.
  2. Prepare the steel. Clean, repair damaged primer, and confirm compatibility with the chosen system.
  3. Protect the site. Mask adjacent suites, seal the work zone, and agree on ventilation, especially for solvent-based coatings.
  4. Apply and measure. Spray in the concealed areas first, then coat exposed members, recording thickness as you go.
  5. Inspect before closing in. Arrange the inspection while the steel is still accessible, then release the area to ceilings and finishes.
  6. Topcoat and touch up. Finish exposed intumescent with the approved topcoat and repair damage from later trades.

For property managers, the questions to ask are about notice periods, after-hours windows, shared systems such as fire panels that may need to be taken offline, and how the contractor will protect neighbours. Our tenant improvement projects are planned around those constraints, and the code side of the schedule is explained in why updating building code compliance matters for owners and contractors.

Our perspective on choosing a system

We approach this choice as the general contractor who has to live with it. Decide first which steel stays visible, then get the rating confirmed, then price both systems for each member. The cheapest product on paper is not always the cheapest once schedule, protection of neighbours and repairs are counted.

On a café, retail or office fit-out, we generally want exposed steel coated and concealed steel sprayed, as long as the listed design allows it. We coordinate the fireproofing contractor, the consultant and the inspector so the steel is signed off before ceilings close.

Our approach is hands-on. We self-perform much of the work and manage the rest under one accountable contract, with WorkSafeBC prime contractor duties, $5M liability coverage and permits handled for you. Property managers get a fixed scope and a clear schedule.

MultigroupTeam

Planning a fireproofing scope with Multigroup

If your project involves rated steel, bring us in at the design stage. We are a Vancouver commercial general contractor delivering tenant improvements, office fit-outs, retail and restaurant buildouts, warehouse renovations and strata common-area work across Metro Vancouver, including phased and after-hours work in occupied buildings.

Multigroup

Send us your drawings or a description of the steel and we will help you scope the fireproofing as part of the whole project, with the permit, inspection and schedule included. See our portfolio for completed work, or contact Multigroup to start a conversation.

FAQ

What is spray fireproofing called?

It is commonly called Sprayed Fire-Resistive Material, or SFRM. It is a mix of binders such as cement or gypsum with lightweight aggregates, sprayed onto structural steel. Contractors and specifications also call it cementitious fireproofing, and the two terms are used interchangeably on most commercial jobs.

How expensive is intumescent paint compared with spray?

Intumescent coatings generally cost several times as much as common spray systems, and the cost rises with the fire rating. Small scopes cost more per unit because mobilization is spread over less steel. Ask for pricing by member and rating in Canadian dollars rather than relying on a general square-foot figure.

Does intumescent paint need to be ULC listed in BC?

Canadian specifications typically call for a ULC listing or testing to ULC S101, and listed designs appear in ULC and cUL directories. The BC Building Code sets the required rating, and your consultant confirms which listed design applies. Check with the authority having jurisdiction if you propose an alternative compliance path.

Can I use both on one beam?

Yes. Designs often use spray on hidden portions and intumescent coating on exposed portions of the same member or building. The combination should be covered by a listed design or accepted by the engineer, so confirm it before tender.