Landlord approval for a commercial fit-out in Vancouver usually means clearing four things before demolition starts: written consent to your drawings, agreement on how the work will follow the building's base-building rules, confirmation of any trades the landlord requires for shared systems such as sprinklers and fire alarm, and a site package of insurance certificates, WorkSafeBC clearance and construction rules. When a tenant is doing the work, the City of Vancouver also needs the owner's signature on the building permit paperwork, so the landlord is part of the permit as well as the lease.

This guide covers the approval process for tenants, landlords and property managers in Vancouver and Metro Vancouver. What the lease says the landlord will build or pay for is covered in our guide to the landlord work letter for tenant improvements.

What does landlord approval for a commercial fit-out cover?

Every lease and building is different, but approval usually has five parts:

  • Design consent: the landlord reviews the tenant's drawings and approves them, approves them with comments, or asks for changes.
  • Base-building compliance: the work must respect the structure, shared systems and any tenant design criteria.
  • Trade requirements: some buildings name the contractors for base-building systems.
  • Site documents: insurance, WorkSafeBC and safety paperwork.
  • Construction rules: hours, elevators, loading, noise, shutdowns and common areas.

The lease, and often a tenant manual from the landlord, says which apply. Read them before design starts, because they shape the drawings, the scope and the price.

Why does the landlord review the drawings before work starts?

The landlord owns the base building and is responsible for the systems every tenant shares, such as structure, fire alarm, sprinklers, electrical service, ventilation and plumbing risers. A new demising wall can change exit paths, and a new ceiling layout can move sprinkler heads and fire alarm devices.

So the landlord usually wants to see the drawings before the permit application goes in, and again if the design changes. Our guide to office tenant improvement drawings explains what that set usually includes.

Landlord approval is not a City permit, and a City permit is not landlord approval. You need both.

What are base-building rules and building manager requirements?

Base-building rules are the landlord's standards for anything that connects to or affects the building outside your suite. They often cover:

  • Standard products for ceilings, doors, hardware, lighting and storefronts.
  • How penetrations through floors and fire-rated walls are made and firestopped.
  • Connections to base-building mechanical, plumbing, electrical and life safety systems.
  • Protection of lobbies, corridors, washrooms and elevators used by other tenants.
  • Close-out documents, such as record drawings and system verification, before the landlord accepts the space.

The building manager turns these into site rules, usually starting with a pre-construction meeting and a worker orientation.

Can the landlord require its own trades for sprinklers and fire alarm?

Many commercial buildings do. Because sprinklers, fire alarm, building automation and some mechanical connections serve the whole building, landlords commonly name the contractors allowed to work on them, or have their own contractor verify the tenant's work.

Permits for that work sit with the trade. In Vancouver, the fire sprinkler permit is applied for by the fire sprinkler contractor, and the City says it is valid only once any required building permit has been issued and a sprinkler contractor has been named. For a fire alarm installation or upgrade, the City requires an electrical permit application before it accepts the building permit application.

The general contractor or construction manager brings those trades into the same scope, sequence and site rules as everyone else. Our guide to fire and life safety in commercial renovations covers that coordination in more detail.

Does the City of Vancouver need the landlord to sign off on the permit?

Yes. The City of Vancouver's permit checklists list an owner's undertaking letter as part of a building permit application. When a tenant is carrying out the project, the City's Schedule E-2 Owner's and Tenant's Undertaking must be signed by both the owner and the tenant and submitted before the building permit is issued.

In the City of Vancouver, the Vancouver Building By-law applies. Elsewhere in Metro Vancouver, the BC Building Code applies and each municipality sets its own permit forms, so confirm the owner authorization each one asks for. Our guide to commercial building permits in Vancouver covers the wider permit process.

What insurance and WorkSafeBC documents do landlords ask for?

Before giving access, building managers commonly ask for:

  • Certificates of insurance: commercial general liability coverage, often naming the landlord and property manager as additional insureds, at the limits the lease or tenant manual sets.
  • A WorkSafeBC clearance letter: WorkSafeBC says a clearance letter confirms a business is registered and paying its premiums, and that hiring a contractor who is not making required payments can leave you liable for premiums on that work. It recommends getting one before and after the work.
  • Prime contractor designation: WorkSafeBC explains that where workers of two or more employers work at the same site, a written agreement should name a prime contractor. If there is no written agreement, the owner is considered the prime contractor.
  • Notice of Project: some construction projects need a Notice of Project filed with WorkSafeBC before work begins. Our Notice of Project guide explains when one applies.

Multigroup Contracting is registered with WorkSafeBC and carries $5M in liability insurance, and we can provide certificates and a clearance letter for the landlord's file.

What construction rules should a tenant expect in an occupied building?

Building rules sit on top of City by-laws. Under Vancouver's Noise Control By-law, construction-related noise on private property is allowed from 7:30 am to 8 pm Monday to Friday and from 10 am to 8 pm on Saturdays, with none on Sundays or holidays unless a noise by-law exception permit is issued. Many landlords also limit noisy work to times when neighbouring tenants are closed. If that falls outside the by-law hours, see our guide to after-hours construction permits in Vancouver.

Building rules also typically cover elevator bookings and protection, loading dock and delivery times, waste bins, booked shutdowns of sprinklers, fire alarm, power or water, dust control, and worker access cards and sign-in.

How do you get landlord approval in place before demo day?

  1. Get the tenant manual, base-building drawings and building rules before design starts.
  2. Find out which trades the landlord requires and include them in pricing.
  3. Send the landlord the same drawings the contractor prices and the City reviews, and log every comment.
  4. Get the owner's undertaking signed with the permit application.
  5. Collect insurance certificates, the WorkSafeBC clearance letter and the prime contractor agreement.
  6. Book the elevator, loading dock and first shutdowns once the permit and landlord approval are both in hand.

Our perspective

Delays at the start of a fit-out often come from approval gaps rather than construction problems: drawings the landlord has not signed, a required trade nobody has priced, or a missing certificate. Multigroup Contracting, a commercial general contractor and fee-based construction manager founded in 2016, tracks landlord approvals alongside the permit so everyone is aligned before demolition. See our tenant improvement services, office fit-outs and retail buildouts, or compare general contractor and construction manager delivery.

Planning a commercial fit-out in Vancouver or Metro Vancouver? Get a free quote, call Multigroup Contracting at 778-819-5933 or email info@multigroup.ca. Our Vancouver office is at 700-838 West Hastings St.

FAQ

Do I need landlord approval before starting a commercial fit-out?

In most cases, yes. Commercial leases commonly require the landlord's written approval of tenant drawings before work starts, and building managers usually need insurance and WorkSafeBC documents before giving access. Your lease and tenant manual set the exact requirements.

Does the City of Vancouver need the property owner to sign a tenant's building permit?

Yes. When a tenant is carrying out the project, the City of Vancouver's Schedule E-2 Owner's and Tenant's Undertaking letter must be signed by both the owner and the tenant and submitted before the building permit is issued.

Can a landlord require its own sprinkler or fire alarm contractor?

Many commercial leases and tenant manuals do. Because sprinklers, fire alarm and other base-building systems serve the whole building, landlords often name the trades allowed to work on them or have their own contractor verify the tenant's work.

What is a WorkSafeBC clearance letter and why do landlords ask for one?

A WorkSafeBC clearance letter confirms that a business is registered with WorkSafeBC and paying its premiums. WorkSafeBC says hiring a contractor who is not making required payments can leave you liable for premiums on that work.

What construction hours apply to a commercial fit-out in Vancouver?

Under the City of Vancouver's Noise Control By-law, construction-related noise on private property is allowed from 7:30 am to 8 pm Monday to Friday and from 10 am to 8 pm on Saturdays, with none on Sundays or holidays unless a noise by-law exception permit is issued.