An office tenant improvement in Vancouver usually needs one coordinated set of drawings that serves three readers: the landlord, who approves the design against the base building; the general contractor, who prices and builds it; and the City, which issues the building permit. At minimum that means architectural floor plans showing existing and proposed conditions, with structural, mechanical, plumbing, electrical and sprinkler drawings added when the scope touches those systems. When one reader gets a different or incomplete version, the quote, the permit or both tend to go off track.

This guide is for office tenants, landlords and property managers in Vancouver and across Metro Vancouver who are planning a tenant improvement (TI) and want to know what drawings to ask for, who needs them and why. If you are still at the planning stage, start with our guide on how to plan an office tenant improvement in Vancouver, or see our tenant improvement services in Vancouver.

TL;DR

  • Architectural drawings are the core of every office TI set. Other disciplines are added as the scope requires.
  • The landlord, the contractor and the City each read the drawings for different things, so one coordinated set should serve all three.
  • In Vancouver, the City's permit checklists spell out what the drawings must show, and incomplete applications are returned.

What drawings does an office tenant improvement usually need?

The exact set depends on the scope, but most office TIs draw from the same list:

  • Architectural: existing and proposed floor plans, a key plan showing where the suite sits on the floor, a reflected ceiling plan when ceilings or lighting change, door and finish schedules, and construction details such as wall types and fire-rated assemblies.
  • Structural: needed when the work affects the structure, for example new openings, heavy equipment or added loads.
  • Mechanical and plumbing: needed when ventilation, heating, cooling or plumbing fixtures are added or moved, such as for a new kitchenette or washroom.
  • Electrical: lighting, power and panel changes, plus exit signs and emergency lighting, which are often shown on the architectural plans as well.
  • Fire protection: sprinkler drawings when heads are moved or added, and fire alarm drawings when devices change.

It also helps to understand the stages a set goes through. Our article on permit drawings versus construction drawings explains why a set that is good enough for a permit is not always good enough to build from.

What does the City of Vancouver expect on office TI permit drawings?

Office tenants in buildings on the City's Tenant Improvement Program (TIPs) list can use a faster permit stream for minor interior renovations. Any commercial office building constructed under a building permit applied for after January 31, 2007 is automatically on the list. The City states that it cannot accept incomplete applications and that they will be returned with a request to resubmit.

The City's Field Review and TIPs minor renovation checklist sets out what the application must include. Among other things, it asks for:

  • Drawings in vector PDF format, generally at 1/4 inch to 1 foot (1:50), with a Vancouver Building By-law analysis on the plans. Scanned, hand-drawn or sketched drawings are not accepted.
  • Floor plans that show existing and proposed layouts, the suite's outside dimensions and total area, room uses and dimensions, furniture and counter layouts, door sizes and corridor widths, and exiting for the new space and the other tenant spaces on the floor.
  • Washroom locations and fixtures, with interior elevations for new accessible washrooms, and all exit signs, emergency lights and fire alarm pull stations.
  • A key plan for floors with multiple suites, a reflected ceiling plan when ceiling work is in scope, and construction details including fire resistance ratings and fire stopping at service penetrations.
  • Professional letters of assurance where required, plus an owner's undertaking letter, or an owner's and tenant's undertaking letter.

Two details catch people out. First, the checklist says fire sprinkler drawings are not accepted with the building permit application; they go with the separate sprinkler permit application. Second, the City issues separate permits for each floor of a commercial renovation project. Projects that are not eligible for TIPs, such as those adding a mezzanine, changing the major occupancy or upgrading fire alarm or sprinkler systems, go through a standard building permit with its own checklist. Our guide to tenant improvement permits in Vancouver covers the permit side in more detail.

When do you need an architect or engineer?

In BC, the Architects Regulation sets out which buildings require an architect, and the Architectural Institute of BC notes that an architect must also be retained for renovations to those buildings unless the work is unrelated to the items the regulation lists. The City's TIPs checklist lists a sealed Schedule B architectural letter of assurance, and a structural one when structural work is in scope. Mechanical letters are needed when heating, ventilation or cooling equipment is proposed, and other disciplines may be requested depending on the scope. When more than one professional seals drawings, a Schedule A confirming the owner's commitment and a coordinating registered professional is also required.

Your design team should confirm which professionals your project needs before drawings start, since adding one later usually means redrawing.

What does the landlord need to see?

In a leased office, the landlord owns the base building, including the structure, the fire alarm and sprinkler systems, the electrical service and the shared mechanical systems. Commercial leases commonly require the landlord to approve tenant drawings before construction, and buildings often have design criteria or a tenant manual covering things like ceiling systems, tie-ins to base-building systems and which trades must do certain work.

Ask the landlord early for base-building drawings and any design criteria, and send drawings for review before the permit application. Landlord comments that arrive after the permit is issued can mean revisions and resubmissions. The lease and any work letter also decide who designs and pays for what, which shapes the drawings. Our guide to the landlord work letter explains what to look for.

What does a general contractor need to price the work?

A contractor needs enough detail to price the same job as every other bidder. Permit drawings show what the City needs to review, but they often leave out finish selections, door hardware, millwork, power and data locations, and who supplies furniture, appliances, cabling and signage. Without those, each bidder fills the gaps differently and the prices stop being comparable.

The most useful set for pricing includes:

  • Existing-conditions drawings based on a site measure, not only old record drawings.
  • A clear split between landlord work, tenant work and work by others, such as furniture or IT.
  • Finish, door and hardware schedules, and millwork elevations.
  • Power, data and lighting layouts coordinated with the ceiling plan.
  • Any landlord requirements for base-building trades, working hours or shutdowns.

Anything still undecided should be listed as an allowance so it is priced the same way by everyone. For more on what moves a price, see our article on what drives cost and schedule on a commercial renovation.

How do you keep the drawings, the quote and the permit in step?

  1. Measure the space first and check it against the base-building drawings.
  2. Confirm the professionals needed for the building and scope before design starts.
  3. Get landlord comments early, ideally on the schematic layout and again on the permit set.
  4. Coordinate all disciplines on one set so the ceiling, lighting, sprinklers and walls agree.
  5. Use one revision log. Number and cloud every change, and send the same revision to the landlord, the bidders and the City.
  6. Answer City review comments fully and update the construction set to match the approved permit drawings.
  7. Plan for close-out. Changes made during construction should end up on record drawings. Our guide to as-built drawings explains what owners should check.

How the project is delivered also affects when the contractor sees the drawings. Under a fee-based construction management approach, the builder can review drawings while they are still being developed. Our article on general contractor versus construction manager explains the difference.

How Multigroup Contracting helps

Multigroup Contracting is a commercial general contractor and fee-based construction manager founded in 2016, with our Vancouver office at 700-838 West Hastings St. We are registered with WorkSafeBC and carry $5M in liability insurance. On office tenant improvements, we review the drawing set before pricing, flag gaps and coordination questions, and coordinate trades, permits, landlord approvals and inspections through to handover. See our tenant improvements, office fit-outs and commercial construction services.

Planning an office TI in Vancouver or Metro Vancouver? Get a free quote, call 778-819-5933 or email info@multigroup.ca.

FAQ

What drawings does an office tenant improvement in Vancouver need?

Most office TIs start with architectural drawings: existing and proposed floor plans, a reflected ceiling plan if the ceiling changes, and construction details. Structural, mechanical, plumbing, electrical and fire sprinkler drawings are added when the scope touches those systems. The City of Vancouver lists what it needs in its permit checklists.

Do I need an architect for an office tenant improvement in BC?

It depends on the building and the scope. BC's Architects Regulation sets out which buildings need an architect, including for many renovations. The City of Vancouver's TIPs checklist lists a sealed Schedule B architectural letter of assurance and points applicants to the Architectural Institute of BC's guidance on when an architect is required.

Are sprinkler drawings submitted with the building permit in Vancouver?

Not for TIPs and field review applications. The City's checklist says fire sprinkler drawings are not accepted with the building permit application and are submitted with the separate sprinkler permit application, which is usually made by the sprinkler contractor.

Why does the landlord need to review office TI drawings?

The landlord owns the base building and its shared systems, such as fire alarm, sprinklers, electrical service and structure. Commercial leases commonly require the landlord to approve tenant drawings before work starts, and the landlord's comments can change the design, so it pays to get them before the permit application and before pricing is final.

Can a contractor price an office TI from permit drawings alone?

A contractor can give a budget from permit drawings, but permit sets often leave out finishes, door hardware, millwork and power and data details. A firm price needs those decisions on paper, or clearly stated allowances for anything still open.