A tenant improvement (TI) scope of work is the written list of what will be built, who builds it, who pays, and what documents the city needs before work starts. In Metro Vancouver, a scope that names the permit route, the landlord and tenant split, and the building rules is the one that keeps schedules and budgets intact. We write and build to that standard on commercial projects across the region.

Multigroup
multigroup.ca
Define Your Tenant Improvement Scope
Multigroup delivers commercial fit-outs across Metro Vancouver, managing permits, building-code compliance and work in occupied buildings.
Visit

TL;DR

  • A TI scope is a contract document: it lists the work, the exclusions, the responsibility split between landlord and tenant, and the permit and inspection steps.
  • “Tenant improvement”, “build-out” and “fit-out” describe the same kind of work. What matters is how precisely the work is defined.
  • Use decides complexity. A restaurant or clinic scope carries far more mechanical and permit detail than an office.
  • Permit rules differ by city. Vancouver, Surrey, Burnaby, Langley and Maple Ridge each set their own requirements.
  • Budget and schedule both depend on the scope being fixed before pricing, so settle the design and permit assumptions first.

Table of Contents

What a tenant improvement scope of work is

A tenant improvement scope of work is the document that turns a lease deal into a buildable project. It describes the interior alterations to a commercial space, assigns each item to the landlord, the tenant or the contractor, and sets the limits of the price. Without it, every party prices a different project.

In practice the scope sits between the lease, the drawings and the construction contract. The lease says what the landlord will contribute. The drawings show what the space will look like. The scope states, line by line, what the contractor will actually do: demolition, framing, ceilings, electrical, mechanical, finishes, millwork, and the permits and inspections that go with them.

For property managers and landlords, a clear scope protects the building. It shows which building systems will be touched, which trades will be on site and when. For tenants, it protects the budget, because anything not written into the scope tends to appear later as a change order.

Build-out, fit-out and tenant improvement: the same work

The terms are used interchangeably. A commercial real estate firm in Toronto notes that the work may be called tenant improvements, a commercial fit-out or a build-out, and that the name matters less than defining the work, responsibilities, documents and conditions attached to the project.

There is a practical distinction some landlords draw. “Tenant improvements” often refers to work done under a lease, usually with a landlord contribution or allowance. “Build-out” more often describes taking a shell or second-generation space to an operating condition, such as a café or retail store. A “fit-out” is the common term in office leasing. The construction is the same: walls, ceilings, services and finishes.

When a broker, a landlord’s work letter and a contractor use different words, check that the scope uses one definition. If the lease promises “landlord’s work” and the contractor’s quote says “base building”, confirm both mean the same items. Most scope disputes start with a mismatch like this rather than with the construction itself.

What the written scope should contain

A complete scope lists inclusions, exclusions, quantities, responsibilities and the documents each trade needs. It should be specific enough that two contractors pricing it would arrive at comparable numbers. The headings below cover what we expect to see in a TI scope for a commercial space.

  • Space and drawings: the address, unit, area and the drawing set the scope is based on, with revision dates.
  • Demolition and prep: what is removed, what is protected, and how debris leaves an occupied building.
  • Partitions, doors and ceilings: new walls, demising walls, ceiling types and heights, and fire-rated assemblies where the code requires them.
  • Electrical and lighting: panel work, new circuits, lighting layout, emergency and exit lighting, and data and low-voltage rough-in.
  • Mechanical and plumbing: HVAC adjustments, diffusers, washrooms, sinks and floor drains, kitchenette connections.
  • Fire protection: sprinkler head moves or additions and any fire alarm devices.
  • Finishes and millwork: flooring, paint, wall finishes, counters, reception desks, shelving and signage backing.
  • Equipment connections: who supplies and who connects tenant equipment such as kitchen appliances, medical equipment or racking.
  • Exclusions: furniture, IT and AV equipment, signage, security systems and any item the tenant supplies directly.
  • Permits, inspections and closeout: who applies, who holds the drawings, which inspections are required, and what the handover package includes.
  • Schedule and access: working hours, loading, elevator booking, noise and dust limits, and any after-hours work.

The exclusions list is as important as the inclusions. Writing “by tenant” or “by landlord” beside each item removes the most common source of disagreement on site.

Landlord’s work and tenant’s work

The scope has to show where the landlord’s responsibility ends and the tenant’s begins. A typical split has the landlord providing base-building items such as main HVAC equipment, ceiling grid and electrical rough-in, while the tenant covers custom millwork, branding features and operating equipment. These splits are set by the lease, so the scope should match the work letter exactly.

A TI allowance is a contribution from the landlord toward construction. It is a lease term and is considered separately from the complete construction scope because it may not cover every improvement. The scope should therefore say which items the allowance applies to, how it is paid (reimbursement, direct to the contractor, or a rent credit), and what the tenant funds above it.

Two more points belong in this section of the scope:

  1. Ownership at lease end. State which improvements stay with the building and which the tenant may remove. This affects the tenant’s restoration obligations and the landlord’s future re-letting costs.
  2. Approvals. Many leases require the landlord’s approval of drawings and of the contractor. List the approval steps in the scope so they appear on the schedule, not as a surprise during permitting.

How scope changes with the use of the space

The type of tenant, more than the size of the space, determines how much engineering and approval a TI needs. An office is usually the lightest scope. Retail, restaurants, medical clinics and industrial users each add systems that must be designed, permitted and inspected.

Office. Partitions, ceilings, lighting, flooring, data cabling and some HVAC rebalancing. Meeting rooms and server rooms add ventilation and electrical detail.

Retail. Sales-floor lighting, dedicated circuits, storefront and entry work, millwork and fixtures, and HVAC sized for the occupant load. Our retail buildout service covers this kind of scope.

Restaurant and café. The heaviest common scope. Kitchen exhaust, make-up air, gas and grease management, washrooms and seating layouts all come into play. In Vancouver, commercial kitchen exhaust documentation is a listed application requirement when a commercial kitchen is added or renovated.

Medical and clinic. Higher ventilation, plumbing at every treatment room, infection control during construction and, for some uses, specialized services. Health authority requirements may apply, so confirm them early.

Warehouse and industrial. Racking, mezzanines, loading doors, office build-ins and fire protection. In Langley, for example, installing racking over 8 feet and adding a mezzanine both require a building permit.

If a scope for a restaurant reads like a scope for an office with a kitchen line added, it is incomplete. The kitchen drives the mechanical design, the permit documents and often the schedule.

How scope changes with the use of the space

Permits: how the scope sets the approval route

In British Columbia, interior alterations to a commercial space generally need a municipal building permit, and the scope determines which route applies. A small interior refresh may qualify for a streamlined stream. Anything touching use, exiting, kitchens, sprinklers or structure moves into the standard process with design professionals involved.

The rules are set by each municipality, so a scope for a unit in Vancouver is not a scope for a unit in Surrey or Burnaby. Here is what the cities publish.

City of Vancouver

Vancouver runs a Tenant Improvement Program (TIPs) for eligible office tenants in listed commercial office buildings. Eligible projects do not need a new development permit and receive an expedited field review. The TIPs building permit must be issued before trades permits can be applied for or construction begins, and a final inspection is required before occupancy. Work must start within six months of permit issuance.

The same page lists what is not eligible: work to kitchens or bathrooms, changes in major occupancy, floor area additions including mezzanines, upgrades to fire alarm or sprinkler systems, seismic upgrading and most major renovations. Those projects need a standard building permit. If your scope includes any of them, plan for the standard route from the start.

For a standard application, the City’s commercial renovation checklist (updated March 2026) lists items such as a Building Code Analysis Report for complex scope, energy compliance documentation, an owner or tenant undertaking letter and, for strata-titled buildings, a strata council letter signed by the chairperson. Strata councils should expect to receive that request from tenants.

Our own guides cover the Vancouver process in more detail: tenant improvement permits in Vancouver and commercial building permits explained.

Surrey, Burnaby, Langley and Maple Ridge

Surrey requires a building permit for alterations within a building. Its Minor Tenant Improvement stream covers small, low-complexity interior work, and a City building official decides eligibility based on scope. Larger projects need a Coordinating Registered Professional, an architect or professional engineer who coordinates design and field reviews and provides the Schedule A required by the BC Building Code.

Burnaby requires a permit for any interior or exterior alteration or change of use. Its tenant improvement guide says Preliminary Plan Approval from Planning may be needed first for use changes, added restaurant seats, mezzanines or increased occupant load, with the building permit application due within 90 days of that approval.

Maple Ridge requires a Building Code Analysis at application, and for personal services, childcare and food service projects, Fraser Health Authority approval. Restaurants also need signed and sealed sprinkler drawings with hydraulic calculations.

Langley (City) requires scale drawings, an owner’s acknowledgement and, where a professional engineer is involved, a Letter of Assurance (Schedule B), as set out in its tenant improvement guide.

The common thread: the scope has to name the permit route, the registered professionals and the approvals from outside the city, such as the health authority or strata council, as scope items with owners and dates.

How long an interior build-out takes

An interior build-out is a sequence: design and pricing, permit review, construction, then commissioning and handover. Published guides put the whole path from signed lease to opening at several months, and permit review is the stage that varies most between cities and between scopes.

As one reference point, a Calgary commercial real estate guide gives typical ranges for each stage: design and pricing 2 to 4 weeks, permits 2 to 6 or more weeks, construction 6 to 12 or more weeks, and commissioning and handover 1 to 2 weeks. Those are Alberta figures and give a sense of the order of magnitude, not a Vancouver promise. Metro Vancouver review times differ by city and by whether the project qualifies for a streamlined stream.

What moves the schedule on a Lower Mainland project:

  • Permit stream. A TIPs or minor TI route is quicker than a full building permit with a Building Code Analysis and registered professional reviews.
  • Long-lead items. Rooftop HVAC units, electrical gear, glazing and custom millwork often set the critical path. Order them as soon as the scope is fixed.
  • Use. Restaurants and clinics need more design, more inspections and often outside approvals.
  • Building access. Elevator bookings, loading windows and after-hours restrictions in occupied buildings stretch the working day count.
  • Scope changes. A change after permit submission can mean revised drawings and another review.

Plan the schedule backward from the opening or possession date, and build the permit stage in as its own line. Our Vancouver office build-out timeline guide walks through the sequencing, and a facility management checklist is a useful companion when you are tracking work orders and asset handover after completion.

Budgeting the scope in Canadian dollars

A TI budget has three parts: construction cost, soft costs and contingency. Construction cost comes from the priced scope. Soft costs cover design, drawings, permit fees, engineering, testing and inspection, signage, IT and moving. Contingency covers what the building reveals once walls are open.

The cleanest way to keep the budget honest is to price a scope that is already complete. A line-item quote tied to the scope headings above lets you compare the quote against the allowance, see what the tenant funds above it, and spot gaps before contracts are signed. A lump sum with a vague description pushes the gaps into change orders.

A few practical rules for the budget:

  1. Price against drawings, not sketches. A test fit is a pre-lease layout study, not a design commitment, so use it to compare spaces and not to fix a construction price.
  2. Match the allowance to the scope. Confirm which line items the TI allowance covers and when it is paid out, so cash flow is clear during construction.
  3. Carry a contingency line. Older buildings in Vancouver can hide existing services, uneven slabs and undocumented alterations. A contingency line belongs in every budget for an existing building.
  4. List soft costs separately. Permit fees, engineering and health authority submissions are real costs that rarely sit inside the contractor’s number.
  5. Show the exclusions in dollars where you can. Furniture, signage, IT and kitchen equipment are often the largest items outside the construction price.

For tenants signing a lease, ask the landlord for the work letter, the base-building description and the allowance terms before the lease is final, so the budget starts from the real scope.

Working in an occupied building

Most Metro Vancouver tenant improvements happen inside buildings that stay open. The scope should therefore include building rules as scope items: working hours, noise and dust control, elevator and loading dock booking, shutdowns of building systems, and access to common areas.

Two items deserve their own lines. First, any shutdown of water, power or fire protection needs notice to the property manager and, for the sprinkler system, a plan to keep the building protected. Second, the prime contractor role under WorkSafeBC. On a multi-employer worksite the prime contractor coordinates health and safety, so the contract should state who holds that role.

Strata buildings add a further step. The City of Vancouver checklist asks for a strata council letter signed by the chairperson, so the scope should allow time for council review and meeting cycles. Phased work and after-hours work, such as noisy demolition at night in a mixed-use building, should be written into the schedule with agreed windows instead of arranged day by day.

Our point of view: scope first, then price

We build tenant improvements, office fit-outs, retail and restaurant buildouts and warehouse renovations in occupied buildings across Metro Vancouver, and the pattern is consistent: a project that starts with a fixed, written scope runs better than one that starts with a number.

That is why we work from a defined scope, clear schedules and one accountable contractor. We manage the City of Vancouver and municipal permits, BC Building Code compliance and WorkSafeBC prime contractor duties, and we self-perform and manage the whole project. Property managers and operators get one point of contact for the permit, the trades and the building rules.

For landlords and tenants, we suggest settling three things before pricing: the permit route, the landlord and tenant split, and the building access rules. Once those are on paper, the construction becomes predictable. We are registered with WorkSafeBC and carry $5M liability insurance, so owners and landlords can accept the contractor without extra paperwork.

MultigroupTeam

Getting a TI scope priced

If you have a lease, a space and a target date, the next step is a walkthrough of the space with the drawings and the work letter. We deliver tenant improvements and leasehold improvements for property managers, landlords, retail chains, restaurant and café owners and business owners in Vancouver, Burnaby, Surrey, North Vancouver, Coquitlam, New Westminster and Langley.

Multigroup

Bring the lease clauses on improvements, the allowance terms and any layout work done so far. We will help turn them into a scope that names the permit route, the exclusions and the schedule. For related Vancouver detail, read our guide on three clauses that prevent permit delays, or contact us to start.

FAQ

What does a tenant improvement scope of work include?

It lists the demolition, partitions, ceilings, electrical, mechanical, plumbing, fire protection, finishes and millwork to be built, with exclusions and who is responsible for each item. It also covers permits, inspections, schedule and site access rules. The more specific the quantities and drawings, the more reliable the price.

Is an interior build-out different from a tenant improvement?

In most Canadian leasing, no. The terms describe the same type of interior construction, and leasehold improvements, fit-outs and build-outs are used interchangeably. Some landlords use “tenant improvement” for lease-funded work and “build-out” for taking a shell space to operating condition. Define the work and responsibilities, whatever name is used.

Do all tenant improvements in Vancouver need a building permit?

Interior alterations to commercial buildings generally do. Vancouver’s TIPs stream offers an expedited review for eligible office tenants, while kitchens, bathrooms, mezzanines and sprinkler or fire alarm work go through the standard building permit. Confirm the route with the City or your contractor before pricing.

How long does an interior build-out take?

It depends on the permit stream, the use and long-lead equipment. A typical path includes design, permit review, construction and handover, and permit review is the stage that varies most between cities. Set the schedule from your possession or opening date, with the permit stage as its own line.

Who pays for tenant improvements?

That is set by the lease. Landlords often contribute a TI allowance toward construction, and the tenant pays for costs above it, plus items such as custom millwork, equipment and signage. The scope should state which items the allowance covers and how it is paid.