A Type I hood captures grease, smoke and heat from cooking equipment, and is built to NFPA 96 with a fire suppression system. A Type II hood only removes steam, heat, moisture and odours from equipment that makes no grease. The appliance line-up decides which one you need, and in Vancouver the City classifies that line-up before it issues a permit.

If you are a landlord, property manager or operator planning a café, restaurant or food-service tenant improvement, this choice shapes your budget, your ceiling and roof work, and your schedule. Here is how the two hoods differ, how Vancouver and the BC Building Code treat them, and how to avoid the mistakes that cost weeks.

Multigroup
Plan Your Restaurant Buildout With Confidence
Multigroup delivers restaurant and café buildouts across Metro Vancouver, including permit management and work in occupied commercial buildings.
Explore Multigroup’s services

TL;DR

  • Type I hoods are for grease-producing cooking (fryers, charbroilers, ranges, griddles). Type II hoods are for heat and steam only (dishwashers, steam tables, some ovens).
  • In Vancouver, Class 1 Cooking Operations need a Type I hood and a Building Permit review. Class 2 operations may use a Type II hood.
  • A Type II hood over greasy equipment is not an acceptable shortcut. Unless you can show the authority having jurisdiction that no grease-laden vapour is produced, an NFPA 96 system is required.
  • Moving a hood or changing the appliance line-up, or even the menu, can trigger a new permit, sealed drawings and a mechanical engineer’s letter.
  • Make-up air, fire suppression and exhaust cleaning access belong in the scope from day one.

Table of Contents

What a Type I hood does

A Type I hood is the grease hood. It removes grease-laden vapours, smoke, heat and moisture from cooking equipment, and it is designed to NFPA 96 so that a grease fire stays contained. If someone asks whether a grease hood is Type I or Type II, the answer is always Type I.

The model code language is short and consistent: a Type I hood collects and removes grease vapours and smoke and is equipped with a fire suppression system. The City of Vancouver describes how that looks physically: a Type I hood is typically externally welded to be liquid-tight, using 18-gauge steel or 20-gauge stainless steel.

In practice a Type I system is more than the canopy. It includes:

  • grease filters or baffles in the hood
  • a welded, liquid-tight duct run to the exhaust point, with cleanout access
  • an exhaust fan rated for the application
  • a chemical fire suppression system tied to the appliances and the gas shut-off
  • make-up air sized to replace what the hood exhausts

That chain of components is why a Type I installation touches several trades and professionals at once.

What a Type II hood does

A Type II hood, often called a condensate or heat hood, removes steam, vapour, heat and odours from equipment that does not produce grease. It is lighter in construction and does not need grease filtration or a fire suppression system. It is not designed to survive a grease fire.

Vancouver’s bulletin describes a Type II hood as designed for heat and steam removal and other non-grease applications, generally seamed rather than welded. The same bulletin notes that a Class 2 operation can be served by a Type II hood with general HVAC ducting, which is a simpler and usually cheaper system than a Type I run.

Typical uses are above dishwashers, steam tables, and some ovens and coffee equipment. In many café and quick-service layouts, the Type II hood is a small part of the job and the Type I decision is the big one.

Type I vs Type II at a glance

The two hoods differ in what they capture, how they are built and what the building department asks for. Use this table as a first screen, then confirm against your actual equipment schedule.

Type I hood Type II hood
Captures Grease, smoke, heat, moisture Steam, heat, moisture, odours
Typical equipment Fryers, charbroilers, ranges, griddles Dishwashers, steam tables, some ovens, coffee makers
Construction Liquid-tight welded joints, 18-gauge steel or 20-gauge stainless Generally seamed
Fire suppression Required, with NFPA 96 compliance Not part of the hood design
Vancouver class Class 1 Cooking Operation Class 2 Cooking Operation
Permit review Building Permit review, K2 checklist Simpler path, still subject to the Building By-law

Which appliances need which hood

The equipment decides the hood. Anything that produces grease-laden vapour or smoke needs a Type I hood. Equipment that produces only heat or steam can sit under a Type II hood. The dividing line is grease, not temperature, and not how “hot” the appliance feels.

A US municipal guide from Bellevue sets out the common split: a Type I hood is required for medium, heavy and extra-heavy duty appliances such as fryers, charbroilers and ranges, while Type II suits light-duty equipment like dishwashers, steam tables, convection ovens and coffee makers. That guide is American, so treat it as an illustration of the logic. In British Columbia, your reference is the BC Building Code, NFPA 96 and the local building bylaw.

Here is how that plays out on the projects we see most often:

  • Café with espresso, a panini press and a convection oven: often a candidate for a lighter ventilation path, but only once the City or the engineer confirms the class. Anything that browns, toasts or grills with fat needs a closer look.
  • Restaurant with a fryer, range and grill: Type I, with suppression, a welded duct and a roof or wall discharge route.
  • Dish room in any food tenant: Type II or equivalent exhaust for steam and heat.
  • Pizza oven: it depends on the fuel, the product and the oven listing. Do not assume Type II. Ask the mechanical engineer and the City early.

How Vancouver classifies cooking operations

Vancouver sorts kitchens into classes of cooking operation, and the class drives the hood type and the permit path. Class 1 means significant smoke or grease-laden vapour and requires a Type I hood. Class 2 means steam or heat without grease. Ventless equipment has its own rules.

Under City of Vancouver Bulletin 2007-005, the main points for an owner are:

  • Class 1: requires a Type I hood and goes through Building Permit review. A K2 checklist is required for all Building Permit submissions involving Class 1 operations.
  • Class 2: produces steam or heat but no grease, and may use a Type II hood.
  • Class 4 (ventless or self-contained): equipment must be listed by an organization such as ULC, cUL or ETL.
  • Owner responsibility: the owner must obtain permits before work starts. The bulletin gives a plain example: if a menu change turns the operation into Class 1, a permit is required.
  • Letter of compliance: the City may require a letter from a mechanical engineer and the owner confirming the proposal matches the designated class before issuing a permit.

Other municipalities use the same class language with their own bulletins. Penticton’s, for example, defines Class 5 as cooking that produces no grease-laden vapour, significant steam or significant heat. If your project is in Burnaby, Surrey, North Vancouver, Coquitlam, New Westminster or Langley, confirm with that city’s building department rather than assuming Vancouver’s rules carry across.

Why a Type II hood over greasy equipment fails

Putting a Type II hood over a grease-producing appliance is the most expensive mistake in this category. It fails plan review, or fails inspection later, and the correction means a new hood, new ducting and suppression. The code puts the burden on you to prove no grease is produced.

The BC Building Code Appeal Board dealt with exactly this question in BCAB #1540. The outcome: an NFPA 96 ventilation system is required unless it can be demonstrated, to the satisfaction of the authority having jurisdiction, that grease-laden vapours are not being produced.

This matters for the questions owners ask most:

  • “It is an induction griddle, so there is no open flame.” The heat source is not the test. If the griddle cooks food that releases grease-laden vapour, expect an NFPA 96 system unless the authority accepts otherwise.
  • “We only cook a few items.” Low volume does not change the class on its own. The engineer documents the line-up and the City classifies it.
  • “The previous tenant had a Type II.” An existing hood is no proof that your menu qualifies. A different appliance line-up is a different operation.

If you are planning ventless equipment to avoid a hood altogether, the listing and the authority’s acceptance both have to be in hand before you commit to the equipment order.

BC Building Code, NFPA 96 and who signs what

In British Columbia, commercial cooking exhaust and fire protection systems must be designed and installed to the BC Building Code, and their use, inspection and maintenance must follow NFPA 96, with stated exceptions. Several professionals have to coordinate, and each signs a part.

The BC Fire Code 2018, Division B Section 2.6 sets that framework, and says certified equipment must be installed and maintained according to its certification. The province’s Guide to Letters of Assurance flags the design and field review of NFPA 96 systems, including chemical fire suppression, as work that often involves several disciplines and coordinated Letters of Assurance. The earlier edition of the guide adds that coordination spans architectural, structural, mechanical, fire suppression and electrical professionals, covering items from exterior louvers to seismic restraints.

For a Type I project, plan on this sequence:

  1. Confirm the equipment schedule and the cooking class with the mechanical engineer.
  2. Confirm landlord approval for roof, wall or shaft penetrations and the exhaust discharge route.
  3. Prepare sealed drawings, the K2 checklist where Vancouver requires it, and any engineer’s letter.
  4. Submit for the Building Permit, and handle any plumbing, gas and electrical permits in parallel.
  5. Install the hood, duct, fan, suppression and make-up air.
  6. Complete the field reviews, inspections and suppression testing before opening.

Our restaurant kitchen ventilation permit checklist goes through the submission side in more detail, and our guide to plumbing permits for Vancouver commercial projects covers the trade permits that run alongside it.

Moving a hood or changing the line-up

A hood that already exists is not a free pass. In Vancouver, relocating a commercial hood or reorganizing the appliance line-up needs a new or revised Building Permit, a completed K2 checklist and sealed drawings from a registered professional. This catches many tenants who take over an existing kitchen.

The Letters of Assurance guide is the source for that requirement as applied in Vancouver. For landlords and property managers, the lesson is to ask incoming food tenants for their equipment list before lease signing, and to hold a copy of the approved ventilation drawings for the unit. It keeps the building’s exhaust and fire protection records honest when tenants turn over.

Make-up air and exhaust cleaning

Every exhaust system needs replacement air, and a Type I system needs an exhaust route that can be cleaned. Both are scope items, not afterthoughts. They affect rooftop space, tenant comfort, utility load and your ongoing maintenance obligations.

Penticton’s bulletin states that the BC Building Code and NFPA 96 require make-up air for all exhaust systems, and that outdoor make-up air introduced to occupied areas in winter must be tempered. The reason is physical: the Minnesota Department of Agriculture explains that an exhaust fan creates low pressure, so enough make-up air is needed to avoid depressurizing the building and back-drafting gas appliances. Though a US document, the principle applies anywhere.

For cleaning, the BC Fire Code requires commercial cooking exhaust systems, including ducts and filters, to be inspected at intervals no greater than 7 days where combustible deposits can accumulate, and cleaned when accumulation creates a fire hazard. That makes access panels and a clear duct route a design question from the start. If the duct cannot be reached, it cannot be cleaned.

In an occupied multi-tenant building, make-up air also affects neighbours. A heavy-use restaurant next to an office tenant needs a plan for noise, odour and discharge location before the engineer finalizes the design.

Make-up air and exhaust cleaning — overview diagram

How the hood choice affects budget and schedule

A Type I system adds cost and time compared with a Type II. It involves a welded duct, a fan, suppression, make-up air and more engineering, review and inspection steps. A Type II system is simpler. Exact costs depend on the unit, the duct run and the building, so get a scoped quote rather than a rule of thumb.

The drivers that move the number are consistent:

  • Duct run length and route: a shaft or roof discharge through several floors costs more than a back-wall discharge.
  • Roof or structural work: fans and make-up air units add load and penetrations that may need a structural review.
  • Landlord approvals: the exhaust path is a building-wide matter, so approval timing can sit on your critical path.
  • Permit review: Class 1 operations go through full Building Permit review, so submitting a complete package matters more than anything else you can do to protect the schedule.
  • Equipment lead times: hoods, fans and suppression components are ordered once the design is settled, and the install can only start when they arrive.

We do not publish fixed prices for this work, because each kitchen is different. What we can give you is a fixed scope, a clear schedule and a list of what the City needs to see.

Our perspective: decide the class before you sign the lease

In our experience on café, restaurant and food-service tenant improvements in occupied Metro Vancouver buildings, the hood is rarely the problem. The problem is that the hood decision is made too late, after the lease is signed and the menu is fixed.

We ask three questions before anything else. What is the full equipment list, including future additions? Where can the exhaust leave the building, and who approves it? Does the City need a Class 1 review for this menu? Answering them early turns the hood from a surprise into a line item.

We self-perform and manage the whole project, so ventilation sits in the same schedule as framing, millwork, plumbing and finishes, not in a separate stream that nobody owns. We are licensed and insured ($5M liability, WorkSafeBC), we handle permit submissions and the coordination with the registered professionals, and we plan loud or disruptive work for after hours when the building needs it.

Our advice to landlords: keep approved ventilation drawings on file for every food unit. Our advice to tenants: never order equipment until the class is confirmed.

— MultigroupTeam

Planning a food-service buildout in Metro Vancouver

If you are scoping a café, restaurant or food-service tenant improvement, we can help you settle the hood type, the permit path and the schedule before you commit. We manage City and municipal permits, BC Building Code compliance and phased work in occupied buildings.

See our restaurant and coffee shop renovation service and our wider tenant improvement work, or contact us with your equipment list and address.

FAQ

Is a grease hood a Type I or Type II?

A grease hood is a Type I hood. It is built to capture grease-laden vapours and smoke, uses grease filtration, and is paired with a fire suppression system under NFPA 96. A Type II hood is not designed for grease.

What is a Type II commercial hood?

A Type II hood is an exhaust-only hood for heat, steam, moisture and odours from equipment that does not produce grease, such as dishwashers or steam tables. It is generally seamed rather than welded. In Vancouver it corresponds to Class 2 cooking operations.

Can I use a Type II hood over an induction griddle or pizza oven?

Not unless you can show the authority having jurisdiction that no grease-laden vapour is produced. BCAB #1540 says an NFPA 96 system is required otherwise. Ask your mechanical engineer and the City before you buy the equipment or finalize the design.

Do I need a new permit if I move my hood or change my equipment?

In Vancouver, yes. Moving an existing commercial hood or reorganizing the appliance line-up needs a new or revised Building Permit, a completed K2 checklist and sealed drawings from a registered professional. A menu change that turns the operation into Class 1 also requires a permit.

Do all commercial kitchens need a hood?

Not always, but the exemption has to be earned. Ventless or self-contained equipment must be listed by an organization such as ULC, cUL or ETL, and the authority having jurisdiction decides whether it is acceptable. Smaller operations may still have to consider worker and patron health under Part 6 of the BC Building Code.