A cold shell (also called a grey shell) hands you the building structure, envelope and little else. A warm shell (also called a vanilla shell) adds base-building systems and some finishes, so the tenant starts closer to move-in. The terms are not standardized, so your lease has to define exactly what is delivered.

That last point is where most budgets go wrong. Two landlords can both say “warm shell” and deliver very different spaces. This guide explains the difference, what each condition means for cost, permits and schedule in Metro Vancouver, and which lease items to pin down before you sign. It is written for tenants, brokers, landlords and property managers planning a first-generation build-out.

Multigroup
multigroup.ca
Scope Your Commercial Build-Out
Multigroup delivers commercial tenant improvements across Metro Vancouver, including office, retail, restaurant, clinic and industrial fit-outs.
Explore commercial fit-outs

TL;DR

  • Cold shell: structure, exterior walls and roof, with minimal or no interior systems. Lower base rent and full design freedom, but the highest build-out cost and the longest permit-and-construction timeline.
  • Warm shell: base-building HVAC, lighting, fire suppression and some finished surfaces are in place. Faster to open, but you design around existing partitions, utility layouts and equipment locations.
  • The labels are a spectrum, not a standard. Get a written delivery schedule that lists every system and stub-out the landlord provides.
  • In the City of Vancouver, the first tenant improvement in a new shell building has its own permit steps, and you cannot occupy before the base building does.
  • Negotiate a tenant improvement allowance either way. Its size should track the work needed to make the space usable.

Table of Contents

What shell space means in a commercial lease

Shell space is a unit delivered unfinished, before a tenant has built it out for a specific business. A shell lease is an arrangement where the tenant accepts a space that is essentially a structural skeleton, as Neufeld Legal describes it. The tenant then pays for, or is credited toward, the interior work.

The condition matters because it sets three things at once: your base rent, your capital outlay and the date you can open. A cheap-looking rate on a cold shell can turn into the more expensive option once you add mechanical, electrical, plumbing and fire-protection work.

You will hear many names for the same few conditions: cold shell, cold dark shell, grey shell, warm shell, vanilla shell, white box. NAI Global’s glossary notes that “cold shell” describes a newly developed or fully gutted building with no existing amenities or interior finishes. Because brokers and landlords use the other labels loosely, treat the name as a starting point and the schedule of work as the contract.

Cold shell: what you get and what you build

A cold shell gives the tenant structure, exterior walls, roof and slab, with minimal or no interior systems such as HVAC, plumbing or lighting, according to Board & Vellum’s overview. In practice, the tenant’s contractor builds almost everything inside the envelope.

A typical cold shell scope for the tenant includes:

  • Demising and interior partition walls
  • Ceilings and ceiling grid
  • Mechanical distribution, ductwork and thermostat controls
  • Electrical panels, distribution and lighting
  • Plumbing rough-in and fixtures beyond what the landlord stubbed in
  • Sprinkler drops, fire alarm devices and emergency lighting inside the suite
  • Flooring, paint, millwork and signage

What cold shell does well is flexibility. A restaurant can place its hood, grease interceptor and walk-in where the workflow wants them. A clinic can lay out plumbing for treatment rooms without fighting existing partitions. A retailer can build a brand-specific ceiling height and lighting plan from the start.

The cost is time and capital. Leasing a cold shell typically offers lower base rent and maximum design freedom, but requires significantly higher upfront capital and a longer permitting and construction timeline than a warm shell. Board & Vellum also points out that code compliance and new utility distribution in raw space often produce unexpected costs that can delay opening by months.

Warm shell: what is already in place

A warm shell includes basic interior infrastructure: HVAC, lighting, finished walls and fire suppression, giving the tenant a partially finished canvas, per Board & Vellum. Typically the fire separations, base-building services and common systems are done, and the tenant adds the layout and finishes that make the space theirs.

In the City of Vancouver, the Certified Professional Program guide gives a useful picture of a “complete” base building before a first tenant improvement. It lists interior base-building construction as complete, including fire separations, building services, fire alarm, sprinkler and standpipe systems, exit signs, base-building lighting and HVAC, and emergency lighting, as set out in the City’s CP program guide. That is close to what many Metro Vancouver landlords mean when they offer a warm or vanilla shell.

The trade-off is fit. Warm shell spaces are often more turnkey, but they limit customization by making the tenant work around existing partitions, utility layouts and HVAC placements. If your business needs a heavy kitchen exhaust, a server room with dedicated cooling or a large open floor, a pre-installed layout can cost you money to undo.

Fixed partitions constrain a warm-shell suite layout

Warm shell vs cold shell at a glance

The two conditions differ most in who carries the cost and the schedule risk. Cold shell shifts capital and permitting time to the tenant in exchange for rent and design freedom. Warm shell shifts some of that to the landlord in exchange for higher rent and fixed infrastructure. This table summarizes the typical differences.

Factor Cold shell (grey shell) Warm shell (vanilla shell)
Base building Structure, envelope, roof Structure, envelope, roof plus base systems
HVAC, lighting, fire suppression Minimal or none inside the suite Installed to a base level
Interior finishes None Some, such as finished walls or ceilings
Base rent Typically lower Typically higher
Tenant capital outlay Highest Moderate
Design flexibility Maximum Limited by existing layouts
Time to open Longest Shorter
Main risk Hidden infrastructure and permit costs Existing systems that do not match your plan

Use this as a guide, not a rule. A “vanilla shell” in one building can include a ceiling and washroom core, while in another it ends at a sprayed slab and capped utilities.

Why the labels are not enough: the delivery condition schedule

The shell condition is a spectrum, so the lease should list each item the landlord delivers. Neufeld Legal stresses that ambiguity over systems and utility stub-outs often leads to disputes over who pays for infrastructure during the build-out. A one-line description such as “warm shell” is not enough.

Ask your broker or lawyer to attach a schedule that answers these questions:

  1. Electrical: What amperage and voltage is available at the suite, and where is the panel or the meter?
  2. HVAC: Is there a rooftop unit, a central loop or only a capped connection? What tonnage is allotted to the suite, and who pays to add capacity?
  3. Plumbing and sanitary: Where are the stubs, what size, and at what elevation? Is there a floor drain and a grease interceptor allowance?
  4. Gas: Is gas available at the unit, and at what capacity? This matters for restaurants and cafés.
  5. Fire protection: Are sprinkler heads installed at base-building layout, and who pays to relocate them to match your partitions?
  6. Fire alarm and emergency lighting: Are devices in place, and who reprograms them?
  7. Telecom: Where does service enter, and what riser access do you have?
  8. Floor and ceiling: Slab condition and load rating, and ceiling height clear of ducts.
  9. Washrooms and exits: Are code-required washrooms and exits finished, or is that tenant work?
  10. Landlord work completion date: What happens to your rent commencement if delivery slips?

HVAC is a good example of why this matters. If the suite relies on an existing rooftop unit, find out its age and service history before you design around it. A rooftop unit maintenance checklist gives property managers a practical list of measurable checks that is worth running through during due diligence on a warm shell.

Permits and approvals for a first tenant improvement in Vancouver

The first tenant improvement in a newly built shell space is a distinct permit situation. In the City of Vancouver, it runs through the building permit process, and many projects use the Certified Professional (CP) Program, which lets a qualified professional certify compliance and can streamline review.

Two points from the City’s own documents shape your schedule:

  • Occupancy follows the base building. The City’s decision tree for CP-3 notes that a TI permit may be issued before the base building occupancy permit, but the tenant space may not receive occupancy ahead of the base building. Do not plan a fixturing or opening date that assumes otherwise.
  • Extra data for shell spaces. The City’s minor renovation submission checklist lists a Building Permit Data Sheet as required for a first tenant improvement in a newly constructed shell space.

Not every job is minor. The City of Vancouver’s Tenant Improvement Program is for eligible buildings and minor renovations. Projects that increase occupant load, affect exiting or involve kitchen or washroom work generally need a standard building permit or a more rigorous professional-led process. Structural changes, fire protection changes and assembly use also trigger a building permit. Other Metro Vancouver municipalities, such as Burnaby, Surrey and Richmond, run their own permit systems, so confirm the local process before you set dates.

For a step-by-step look at the approvals, see our guides on the tenant improvement permit process in Vancouver and on navigating Vancouver permits and renovations.

Budget and schedule: how shell condition changes both

The shell condition moves your costs between two buckets: base rent and build-out. A cold shell lowers the first and raises the second. The difference is rarely small, because a cold shell tenant pays for systems that a warm shell already has.

We do not quote a single per-square-foot number for shell conversions, because scope varies too much by use. A restaurant with a hood and grease interceptor is a different project from a quiet office. For a range across commercial renovation types, see our breakdown of commercial renovation cost per square foot in Vancouver. Build your own number from a written scope, not from the label.

Build the budget and schedule from these lines:

  • Design and engineering: architect, mechanical, electrical and plumbing engineers, and the Certified Professional if used.
  • Permit and fees: building permit and any trade permits.
  • Construction: the tenant’s contractor scope, including site supervision and WorkSafeBC obligations.
  • Long-lead items: switchgear, rooftop units, kitchen equipment and storefront glazing. Order early.
  • Contingency: keep a reserve for conflicts between existing systems and your plan.

On schedule, cold shell adds the most risk at the front end: new utility distribution, engineering coordination and a longer permit review. Warm shell shortens that sequence, but the early review of existing systems still matters. A government technical standard for tenant improvements, the BC Real Property Division’s office standards, sets design temperatures and equipment expectations that show why you should check existing HVAC against your use rather than assume it fits.

Tenant improvement allowances: negotiate them for either shell

A tenant improvement allowance is money the landlord contributes toward your build-out, usually credited against costs or amortized into rent. The BDC advises commercial tenants to negotiate an allowance regardless of the shell type, since landlords often offer inducements to secure long-term, high-quality tenants.

The size should reflect how much work it takes to make the space usable. A cold shell normally supports a larger allowance than a warm shell because the tenant must install more. Before you agree to terms, settle these points:

  • Is the allowance paid on completion, in draws or as rent credit?
  • Does it cover soft costs like design and permits, or only hard construction?
  • What happens to unused allowance?
  • Who owns the improvements at the end of the term, and must you remove them?
  • Does the landlord need to approve your plans and contractor, and how fast must they respond?

Landlord approval timelines are an overlooked schedule item. Our article on three lease clauses that prevent tenant improvement permit delays covers how to keep that step from stalling your project.

Our perspective: scope the gap before you sign

We are a commercial general contractor in Vancouver, and we see the same pattern on shell projects. The label on the listing is not the risk. The gap between what the landlord delivers and what the tenant’s business needs is the risk, and it is cheapest to find before the lease is signed.

Our advice to tenants, brokers and property managers:

  1. Walk the space with a contractor before you commit. A site walk with a GC and the design team turns a vague “warm shell” into a list of what stays, what moves and what has to be added.
  2. Price the build-out, not just the rent. Compare total occupancy cost over the term, including capital, allowance and downtime before opening.
  3. Test existing systems against your use. Cafés and restaurants, clinics and light industrial users load electrical, ventilation and plumbing differently from offices.
  4. Plan the sequence around occupancy. In an occupied building or a phased new development, noise, deliveries, shutdowns and after-hours work have to be agreed with the property manager early.
  5. Name one accountable party. We self-perform and manage the whole project, so permits, trades, the WorkSafeBC prime contractor role and the schedule sit with one team.

For landlords, the lesson runs the other way. A clear, itemized delivery schedule lowers disputes, speeds up leasing and makes your allowance conversation more concrete. That helps you close tenants who would otherwise stall over unknowns.

— MultigroupTeam

Safety and site duties during a shell build-out

A shell build-out is a construction site, even when the rest of the building is operating. In British Columbia, the prime contractor and each employer have defined health and safety duties, and a first aid assessment is part of that. WorkSafeBC states that an employer must complete a written first aid assessment for each workplace, and different workplaces can have different requirements.

For a tenant space inside a larger building, do not rely on the base building’s first aid supplies. Your project’s own risks, such as cutting, welding, lifting or working alone, set what you need. Ask any contractor you consider how they handle prime contractor duties, site access control and dust and noise management around neighbouring tenants.

Choosing between warm and cold shell: a quick decision guide

Choose based on how specialized your use is and how soon you need revenue. Warm shell suits businesses with standard layouts that want a shorter route to opening. Cold shell suits specialized users who benefit from designing every system, and who can fund the build-out and carry the longer timeline.

A warm shell usually fits when:

  • Your layout is conventional, such as general office or standard retail.
  • Opening date matters more than perfect workflow.
  • You want less capital at risk up front.

A cold shell usually fits when:

  • You need heavy or unusual building services, such as kitchen exhaust, extra power or specialized plumbing.
  • You are building a flagship or a brand-specific space and want full control.
  • The landlord offers a strong allowance and a lower rate that offsets the extra work.

If you are unsure, ask for both: have the broker request a delivery schedule, then ask a contractor for a rough scope and schedule for that space. A few hours of review often saves months.

Plan your shell build-out with Multigroup

We deliver tenant improvements and fit-outs across Metro Vancouver for offices, retail stores, restaurants and cafés, clinics and warehouses. We handle City of Vancouver and municipal permits, BC Building Code compliance and phased or after-hours work in occupied buildings, with fixed scope and a clear schedule.

If you are comparing a warm shell with a cold shell, we can review the space and the lease schedule with you. Start with our tenant improvement services, or see our work on retail buildouts and restaurant and café renovations. To discuss a specific space, contact us.

FAQ

What does warm shell mean?

A warm shell, also called a vanilla shell, is a commercial space delivered with base-building systems such as HVAC, lighting and fire suppression, plus some finished surfaces. The tenant completes the layout, finishes and specialty systems. What is actually included varies by building, so the lease should list it.

What is cold shell construction?

Cold shell construction delivers the structure, exterior walls and roof with minimal or no interior systems. Mechanical, electrical, plumbing and fire protection inside the suite are installed later, usually by the tenant’s contractor. It gives the most design freedom and requires the most capital and time.

Is grey shell the same as cold shell?

In most usage, yes. Grey shell and cold shell (or cold dark shell) describe the same minimal condition, while vanilla shell and warm shell describe the more finished one. Some landlords use the words differently, so rely on the written delivery schedule rather than the label.

Does a warm shell still need a building permit for tenant work?

Usually, yes. In the City of Vancouver, the first tenant improvement in a new shell space follows the building permit process, and work that changes structure, fire protection, exiting or occupant load needs a standard permit. Confirm requirements with the municipality where the unit sits.

Who pays for the build-out in a shell lease?

The tenant normally pays, often with help from a landlord’s tenant improvement allowance. The size of the allowance and what it covers are negotiated, and they tend to track the amount of work needed to make the space usable. Put every landlord obligation in writing.