Hardwood Giant — Two Flooring Showrooms
Vancouver and Richmond, BC — Full showroom fit-outs for two new Hardwood Giant locations, delivered back-to-back on new leases against fixed opening dates.
Project specification
- Client: Hardwood Giant
- Sector: Retail buildout — flooring showrooms
- Location: Vancouver and Richmond, BC
- Size: Approximately 4,000 sq ft per showroom (80 × 50 ft), 8,000 sq ft across both
- Contract value: $150,000 per showroom ($300,000 across both locations)
- Engagement: General contractor for both locations, delivered back-to-back with the same crew
- Condition: New leases; stores closed to the public during construction
Overview
Hardwood Giant took on two new leases — one in Vancouver, one in Richmond — and needed both spaces turned from empty retail units into working flooring showrooms with staff areas behind them. Multigroup Contracting was the general contractor for both locations, running the projects back-to-back with the same crew so the second store benefited from everything learned on the first.
Related services: Retail buildouts · Tenant improvements
Scope
Showroom millwork
Full-height flooring display walls and sample racks built to show hardwood, laminate and vinyl ranges.
Lighting and electrical
New showroom lighting layout, with panels and circuits sized for display and back-of-house loads.
Partitions and back-of-house
Demising and partition walls, offices, staff areas and washrooms.
Front of house
Storefront, signage, ceiling and paint throughout.
The challenges
Both stores had committed launch dates, and the two builds ran back-to-back on new leases.
Fixed opening dates: both stores had committed launch dates, so the schedule was built backwards from opening day and material lead times were locked in before demolition started.
Two stores in sequence: the Richmond and Vancouver builds ran back-to-back, which kept one crew continuously on Hardwood Giant work and let the second store move faster than the first.
Permits and landlord approvals: each unit required its own municipal permit path and landlord tenant-improvement sign-off, coordinated so approvals landed before the trades needed them.
Outcome
Both showrooms opened on their committed dates as fully fitted retail spaces — display walls, lighting, offices, washrooms and storefront complete — on new leases that started as empty shells. The stores were closed to the public during construction, so the work ran at full pace without phasing around customers.
Planning a retail buildout or showroom in Metro Vancouver? Talk to us about your opening date first. CONTACT US