An office TI close-out package is the set of records handed to the tenant and the landlord when a tenant improvement is finished: the occupancy permit or final inspection approval, letters of assurance from the design professionals, sprinkler and fire alarm test records, as-built drawings, warranties, operation and maintenance manuals, and a signed-off deficiency list. In Vancouver, most landlords expect this package before they treat the space as accepted, so the simplest approach is to plan it at the start of the project rather than assemble it at the end.
This guide is for office tenants, landlords and property managers handing over a commercial office tenant improvement or fit-out in Vancouver and elsewhere in Metro Vancouver. Design professionals, trade contractors and the general contractor each produce part of the package, and the general contractor usually collects and organizes it.
What is a close-out package for an office tenant improvement?
Handover has two halves: the physical space and the paperwork that proves it was built and approved properly. The close-out package is the paperwork half. It shows that permits were closed, that the professionals who designed the work reviewed it in the field, that life safety systems were tested, and that the tenant knows how to look after what was built.
The landlord's list usually comes from the lease or the work letter. Our guide to the landlord work letter for a tenant improvement explains where those requirements sit, and the landlord approval guide covers the rules agreed before work starts. Reading both early tells everyone which close-out documents the landlord will ask for, in what format and to whom.
Which City approvals close out an office TI in Vancouver?
The City of Vancouver says an occupancy permit must be issued before anyone occupies space in a commercial building when the work creates new space, is a major renovation or changes the proposed use of the space. The requirements listed on your building permit say whether one applies. The City also notes that approvals from other departments and agencies, such as a Vancouver Fire and Rescue Services fire prevention inspection, may be needed before the occupancy permit is issued.
For minor office renovations permitted through the City's Tenant Improvement Program (TIPs), a final inspection is required before occupancy is allowed. Separate trade permits for plumbing, electrical, gas and fire sprinkler work are inspected on their own, and their final approvals belong in the package too.
Keep a copy of the occupancy permit or final inspection record, and of each trade permit final, in the package. Our guide to occupancy permits in Vancouver covers the permit itself in more detail.
What letters of assurance and test records go in the package?
The Province's guide to letters of assurance under the BC Building Code 2024 and the Vancouver Building By-law 2025 says alterations to existing buildings, including tenant improvements, need letters of assurance when the work involves components within the scope of Division C, Subsection 2.2.7. When they apply:
- Schedule C-B: each registered professional of record submits one for their discipline after the project is complete but before the authority having jurisdiction issues an occupancy permit or makes a final inspection.
- Schedule C-A: the coordinating registered professional confirms they coordinated the field reviews and the functional testing of fire protection and life safety systems. The guide notes that simple alterations and tenant improvements may not need a coordinating registered professional.
The City's sample occupancy submission checklist, written for a typical complex building, also lists records such as sprinkler material and test certificates, a backflow preventer test report, a fire alarm certificate of verification and inspector clearances. An office TI usually needs only the items that match its scope, but landlords tend to ask for copies of anything that touched base building sprinkler and fire alarm systems.
What should as-built drawings show for an office TI?
As-built drawings record what was actually built, which is not always what the permit drawings showed. For an office tenant improvement, they should show:
- Wall locations, door sizes and hardware, and any fire separations.
- Reflected ceiling plans with lighting, sprinkler heads, diffusers and access panels.
- Power and data outlets, floor boxes, circuits and updated panel schedules.
- Plumbing routes, shutoff valves and any slab cores or concealed services.
Agree the format with the landlord early, for example PDF and CAD files that follow the building's standards. Our guide to as-built drawings explains what commercial owners check, and the office tenant improvement drawings guide covers the original drawing set the as-builts update.
Which warranties and manuals do landlords and tenants expect?
The contract sets the general contractor's warranty and when it starts. On top of that, the package usually collects:
- Trade and manufacturer warranties for items such as flooring, doors and hardware, millwork, lighting controls, access control and appliances.
- Operation and maintenance manuals with product data, finish schedules, paint colours and cleaning instructions.
- Spare materials the landlord or tenant asked for, such as ceiling tiles, carpet tiles and paint.
- Keys, access cards and lock records, plus a contact list for each trade contractor.
A single warranty register makes these easier to track after the move-in. See our guide to construction warranties for commercial owners for how to set one up.
How does the deficiency walk work at handover?
The deficiency walk is a room-by-room review of the finished space with the tenant, the designer and, usually, the landlord or property manager. Each item is recorded with its location and the trade responsible, then corrected and checked again until the list is signed off.
Landlords often add their own base building checks to the walk:
- Ceiling tiles back in place and sprinkler heads clear and undamaged.
- Firestopping complete where new services pass through fire separations.
- Electrical rooms, risers and shared corridors left clean and restored.
- Elevator protection, debris and construction signage removed.
Our guide to commercial punch lists covers how to run the list in an occupied building.
What payment and legal records come with close-out?
Close-out also covers the paperwork that lets the final payments go ahead. Under the BC Builders Lien Act, the owner retains a holdback from payments, and a payment certifier can issue a certificate of completion once a contract or subcontract is substantially completed. That certificate starts the holdback period for the contract. Our guide to builders liens in BC explains the holdback rules.
WorkSafeBC advises getting a clearance letter before and after a contractor provides services, because a business that hires a registered contractor who is not paying premiums could be liable for premiums related to that work. Many landlords and tenants ask for a current clearance letter with the final invoice, along with any other closing documents the contract lists.
How do close-out rules differ in Burnaby and Richmond?
- Burnaby: the City says interior alterations to an existing commercial building, including tenant improvements, need a building permit. Its building permits and inspections guide says that once all final inspections are complete, the building inspector may issue a certificate of occupancy.
- Richmond: the City's Building Regulation Bylaw says a building may not be occupied until the building inspector has issued an occupancy certificate. Its inspections guide says plumbing, gas and electrical finals must be approved before the final building inspection, and the documents for that inspection may include Schedule C letters of assurance.
Other Metro Vancouver cities have similar steps, so confirm the close-out requirements on your own permit.
What should your office TI close-out checklist include?
- The landlord's close-out list from the lease or work letter, with format and delivery details.
- The occupancy permit or final inspection approval, plus every trade permit final.
- Letters of assurance and sprinkler and fire alarm test records, where they apply.
- As-built drawings in the format the landlord asked for.
- Warranties, operation and maintenance manuals, spare materials, keys and access cards.
- A signed-off deficiency list, including the landlord's base building items.
- Holdback and certificate of completion records, and current WorkSafeBC clearance letters.
A complete package also helps later, when the lease ends. Our guide to commercial lease make-good and restoration shows why good records make that handover easier.
How Multigroup Contracting helps
Multigroup Contracting is a commercial general contractor and fee-based construction manager with our Vancouver office at 700-838 West Hastings St. Founded in 2016, we are registered with WorkSafeBC and carry $5M in liability insurance. On office tenant improvements, we confirm the landlord's close-out list at the start, collect permit finals, test records, as-builts, warranties and manuals from the design team and trade contractors as the work progresses, and run the deficiency walk with the tenant, the designer and the landlord. We deliver tenant improvements and office fit-outs as a general contractor or through construction management in Vancouver and across Metro Vancouver, including Burnaby and Richmond.
Planning an office tenant improvement in Vancouver or Metro Vancouver? Get a free quote, call Multigroup Contracting at 778-819-5933 or email info@multigroup.ca.
FAQ
What is included in an office TI close-out package?
A typical office tenant improvement close-out package includes the occupancy permit or final inspection approval, trade permit final inspections, letters of assurance from the registered professionals, sprinkler and fire alarm test records, as-built drawings, warranties, operation and maintenance manuals, spare materials, keys and access cards, and a signed-off deficiency list. The lease or work letter often lists exactly what the landlord expects.
Do I need an occupancy permit after an office tenant improvement in Vancouver?
Often, yes. The City of Vancouver says an occupancy permit must be issued before occupying space in a commercial building when the work creates new space, is a major renovation or changes the use of the space. The requirements listed on your building permit tell you whether one applies, and an office renovation under the Tenant Improvement Program needs a final inspection before occupancy is allowed.
Who signs the letters of assurance at the end of a tenant improvement?
When the work falls within the scope that requires letters of assurance, each registered professional of record, such as the architect or the mechanical, electrical or fire suppression engineer, signs a Schedule C-B for their discipline after the work is complete. Where a coordinating registered professional is involved, they sign a Schedule C-A. These go to the City before it issues an occupancy permit or makes a final inspection.
What is the difference between a deficiency list and a close-out package?
A deficiency list records the work that still needs fixing or finishing after the handover walk, such as damaged finishes, missing hardware or ceiling tiles out of place. The close-out package is the full set of records handed over at the end: permits, inspection approvals, letters of assurance, drawings, warranties and manuals. A signed-off deficiency list is usually one of the documents inside the package.
Why do landlords ask for as-built drawings after an office fit-out?
Landlords keep as-built drawings as a record of what changed in their building: new walls, ceilings, sprinkler heads, power, data and any concealed services. They use them for building operations, for future tenants and for make-good at the end of the lease, so they usually want them in an agreed format before they accept the space.
Sources
- Get an occupancy permit, City of Vancouver
- Tenant Improvement Program (TIPs), City of Vancouver
- Occupancy Permit Submission Documents Checklist (sample for typical complex building), City of Vancouver
- Guide to the Letters of Assurance in the BC Building Code 2024 and Vancouver Building By-law 2025, Province of British Columbia
- BC Building Code 2024, Province of British Columbia
- Builders Lien Act, BC Laws
- Why do I need a clearance letter?, WorkSafeBC
- Commercial Renovations, City of Burnaby
- Building Permits and Inspections, City of Burnaby
- Building Regulation Bylaw No. 7230, City of Richmond
- Inspections Required: Building, Plumbing, Gas and Site Services, City of Richmond