Combining two adjacent commercial suites usually means removing or opening the demising wall between them, then making the larger space work as one suite: exits and washrooms that suit the new occupant load, one sprinkler and fire alarm layout, and building systems that serve a single tenant. In Vancouver, it also needs your landlord's approval and, in most cases, a building permit, and how the City classifies the renovation decides the permit path. Sort out the code review and landlord approval before you commit to the expansion.

This guide is for office, retail, restaurant and industrial tenants, landlords and property managers in Vancouver and Metro Vancouver who are joining two units into one. If you are splitting a space instead, see our guide to commercial demising walls.

What changes when two commercial suites become one?

Two suites built for two tenants are set up to run separately, each with its own entrance and exits, electrical panel and share of the building's sprinkler, fire alarm, heating and ventilation systems. The demising wall between them separates the two tenancies and is often a rated fire separation.

Joining them creates a single suite, so the main questions are:

  • What happens to the demising wall.
  • Whether the exits and washrooms suit the combined occupant load.
  • How the building systems will serve one tenant instead of two.
  • What the landlord, the lease and the permit require.

Can you simply remove the demising wall?

Not before a few checks. Before any demolition, confirm:

  • Structure: whether the wall carries loads or braces the structure. If there is any doubt, a structural engineer reviews it.
  • Services inside the wall: electrical, plumbing, sprinkler piping, ductwork or data that may need to be rerouted.
  • Full or partial removal: some layouts only need a wide opening. Your designer confirms whether any part of the wall that stays still needs its fire rating.
  • The walls that stay rated: the walls between the combined suite and the corridor or neighbouring tenants keep their required separation, so new openings and penetrations in them must follow the approved assembly.

Under WorkSafeBC rules, a qualified person must conduct a hazardous materials survey before any renovation or demolition work. The Occupational Health and Safety Regulation, Part 20 puts that duty on the owner and the employers responsible for the work, with a written report of what was found, such as asbestos or lead. If either is present, it has to be dealt with safely before the wall comes down, and certain asbestos and lead work also needs a WorkSafeBC Notice of Project.

How do exits, occupant load and washrooms change?

A bigger floor area and a new layout change the occupant load, and the occupant load drives several design decisions:

  • How many exits the suite needs, how wide they are and how far apart.
  • Door swing and hardware.
  • The number of washroom fixtures.
  • Whether fire alarm requirements change.

Exits that each served a separate suite may not work for the combined one; two doors that end up close together can count as a single exit. Our guides to occupant load calculation in BC and washroom fixture counts explain how these numbers are worked out, and our guide to fire and life safety in commercial renovations covers how exits, rated walls, sprinklers and fire alarm shape a layout.

A change of use matters too. Turning office or retail space into a restaurant or café as part of the expansion can change the major occupancy, which affects the permit path.

How do the building systems come together?

Each system has to serve one suite, and the designer, engineers and landlord make most of the decisions:

  • Sprinklers and fire alarm: removing a wall changes sprinkler coverage and where alarm devices need to be. In Vancouver, any change to sprinkler system piping requires a fire sprinkler permit, and the sprinkler contractor applies for it.
  • Electrical: two suites usually mean two panels. Whether to keep both or consolidate is decided with the landlord.
  • Heating and ventilation: the landlord's requirements and a mechanical engineer decide how the base-building systems serve the combined layout, and specialist trades carry out that work.
  • Plumbing: duplicate washrooms or kitchenettes may stay, be removed or be relocated.

The City of Vancouver notes that most construction is likely to require separate trades permits, such as plumbing, electrical, gas and fire sprinkler, typically submitted by the trade contractors hired by the general contractor.

What does the landlord need to approve?

Removing a demising wall changes the landlord's building, so expect to need written approval of the drawings before work starts (see our guide to landlord approval for a commercial fit-out). Also settle:

  • The lease: whether the two suites move to one lease or an amendment, and who pays for what under any landlord work letter.
  • Restoration at the end of the lease: whether the landlord will want the wall put back. Our guide to make-good and restoration explains why to agree this in writing now.
  • The suite number: the City of Vancouver only changes an address when there is a major access problem for emergency responders, Canada Post or delivery services, or when the original number was assigned in error. Agree which suite number the combined premises will use for the lease, signage and deliveries.

What permits and inspections does combining suites need in Vancouver?

The City of Vancouver says renovations that move interior walls, and tenant improvements to commercial space, generally need a permit. What matters next is how the project is categorized.

Work on existing buildings in Vancouver falls under Part 11 of the Vancouver Building By-law. The Notes to Part 11 describe a minor renovation as work within a single suite and its shared demising walls. They list relocating a shared demising wall and subdividing a single-storey suite as minor renovation work, but not joining two suites into one. Renovations that fall outside the defined categories are major renovations, which carry their own upgrade requirements. Your designer or code consultant confirms which category applies.

That category also shapes the permit stream:

  • TIPs: the City's Tenant Improvement Program is a dedicated stream for office tenants in eligible buildings doing minor interior renovations. It excludes most major renovations, changes in major occupancy, assembly occupancies that increase occupant load or affect exiting, and projects that upgrade existing systems, fire alarms or sprinkler systems.
  • Standard building permit: if the project does not qualify for TIPs, it needs a standard building permit.
  • Inspections: the work is inspected at stages through to a final inspection.
  • Occupancy: the City requires an occupancy permit before occupying space in a commercial building after major renovations, a change of use or when new space is created.

Our tenant improvement permit guide and our guide to office tenant improvement drawings cover the application in more detail. Elsewhere in Metro Vancouver, the 2024 BC Building Code applies and each municipality runs its own permit process.

How Multigroup Contracting helps

Multigroup Contracting is a commercial general contractor and fee-based construction manager with our Vancouver office at 700-838 West Hastings St. Founded in 2016, we are registered with WorkSafeBC and carry $5M in liability insurance. When you are joining two units, we walk both suites with your designer, coordinate the consultants and trades, and work through landlord approval, permits and inspections. We build tenant improvements, office fit-outs and retail buildouts across Metro Vancouver.

Planning to combine two commercial suites in Vancouver or Metro Vancouver? Get a free quote, call Multigroup Contracting at 778-819-5933 or email info@multigroup.ca.

FAQ

Do I need a permit to combine two commercial suites in Vancouver?

In most cases, yes. The City of Vancouver generally requires a permit for renovations that move interior walls and for tenant improvements to commercial space. Electrical, plumbing and sprinkler changes need their own trade permits.

Can I use the City's Tenant Improvement Program (TIPs) to combine two office suites?

Only if the project qualifies. TIPs is for minor interior renovations by office tenants in eligible buildings, and it excludes most major renovations and projects that upgrade fire alarm or sprinkler systems. Otherwise, you need a standard building permit.

Is the demising wall between two suites a fire separation?

Often, yes. A demising wall between two tenancies is commonly a rated fire separation. When the suites become one, the walls between the combined suite and its neighbours keep their required separation.

Will the combined suite get a new address?

Usually not. The City of Vancouver only changes an address for a major emergency or delivery access problem, or an error in the original number. Agree with your landlord which suite number to use.

Do I need a hazardous materials survey before removing a demising wall?

Yes. WorkSafeBC requires a qualified person to inspect for hazardous materials, such as asbestos and lead, before renovation or demolition work begins, and to provide a written report of what was found.