Nail Salon Buildout in Metro Vancouver
Metro Vancouver, BC
Quick answer: Multigroup Contracting delivered a nail salon tenant improvement in an approximately 2,000 sq ft empty commercial unit in Metro Vancouver. The buildout included custom reception millwork and nail stations, backlit polish displays, lighting, porcelain tile flooring and an accessible washroom. Retail buildouts · Tenant improvements · Commercial construction · Get a free quote
Project at a glance
- Project type: Nail salon tenant improvement (full buildout)
- Client: Nail salon (beauty and personal care)
- Location: Metro Vancouver, BC
- Size: About 2,000 sq ft
- Starting point: Empty commercial unit
- Schedule: 6 weeks of construction
- Outcome: Finished on time and on budget
- Our role: General contractor, managing all trades with one point of contact
- Special conditions: High ceilings, so overhead work was done from scaffolding
Overview
A nail salon had leased an empty commercial unit and needed it turned into a bright, polished space ready for clients. As the general contractor, we managed every trade on the job and gave the client one point of contact from the first day of construction to handover.
Related services: Retail buildouts · Tenant improvements · Commercial construction
What was the challenge?
The unit was an empty shell. Everything a nail salon needs had to be built in: a reception area, nail stations, polish displays, storage, lighting, flooring and a washroom.
A salon is also a design-led space. Clients judge it the moment they walk in, so the custom counters, feature walls and lit displays had to be built cleanly and fit together exactly.
Two things shaped the schedule. The porcelain and laminate finishes were imported from China, so they had to be ordered early and the work sequenced around their arrival. And the unit's high ceilings meant much of the overhead work could only be done from scaffolding.
What did this nail salon tenant improvement include?
We delivered the project as a complete salon buildout, managed and delivered with our trade partners. Here is what was included.
Custom reception counter
A custom reception counter with a waterfall-edge, stone-look porcelain top and a curved wood-look laminate feature panel, set in front of the salon's feature wall.
Slat wall feature
A tall feature wall of wood-look laminate slats behind reception, with matching custom back counters and cabinets below it.
Backlit polish displays
Custom wall niches for nail polish, finished in wood-look laminate and lit with LED strip lighting, including a display that wraps around a corner.
Custom nail stations and storage
Custom manicure and nail stations with drawers and built-in outlets, plus back counters with drawers and porcelain tops for storage and supplies.
Accessible washroom
One accessible washroom with a floating porcelain vanity, built to suit the new layout.
Lighting
Track lighting throughout and a feature pendant light over reception, so colours read true at every station.
Flooring and finishes
Large-format grey porcelain tile flooring and freshly painted walls for a clean, bright finish.
Imported materials
The porcelain and laminate finishes were imported from China. We ordered them early and planned the work around their delivery.
Trade coordination
As general contractor, we managed every trade on site. The client dealt with one point of contact, not a list of separate trades.
How did the high ceilings affect the build?
The unit's high ceilings meant much of the overhead work had to be done from scaffolding, and we planned for that from the start.
Lighting, overhead finishes and the upper parts of the tall feature walls are out of reach from a ladder in a space like this. Working from scaffolding is safer and gives the trades a stable platform, but it takes floor space and time to set up and move.
We sequenced the overhead work so the scaffolding could come down before the finished floor, counters and stations needed the space. That kept the trades moving and the job on its six-week schedule.
For anyone planning a salon in a unit with high ceilings, the lesson is simple: allow for scaffolding in the plan and the schedule, rather than discovering it on site.
What were the results?
- An empty unit turned into a finished nail salon of about 2,000 sq ft
- Completed in six weeks
- Finished on time and on budget
- Custom reception counter, slat wall, nail stations and backlit polish displays
- One accessible washroom with a floating porcelain vanity
- High-ceiling work done safely from scaffolding
- One point of contact for the client from start to finish
Nail salon buildout photos







Frequently asked questions
Where was this nail salon tenant improvement?
The documented location is Metro Vancouver, BC. No specific municipality is identified in this case study.
What was Multigroup Contracting’s role?
Multigroup Contracting was the general contractor, managing the trades and coordinating the buildout of the empty commercial unit.
What custom millwork was included?
The project included a reception counter, slat feature wall, nail stations, back counters and backlit polish displays, using porcelain and laminate finishes.
What flooring and accessibility work was included?
The salon received large-format grey porcelain tile flooring and an accessible washroom with a floating porcelain vanity.
Related guides
- Accessible washroom requirements under the BC Building Code
- Commercial restroom layout guidelines
- Tenant improvement permits in Vancouver
- Retail lighting design
- Commercial flooring options
- Construction project management in Metro Vancouver
Planning a salon or retail buildout in Metro Vancouver?
Multigroup Contracting is a commercial general contractor serving Metro Vancouver since 2016. We are WorkSafeBC registered and carry $5 million in liability insurance. We build salons, retail stores and tenant improvements, from empty units to finished spaces with custom millwork, lighting and accessible washrooms. Call 778-819-5933 or contact us to talk about your space. CONTACT US
Portfolio · Home · Blog · Service Areas · Contact