Retail Flooring Showroom Buildout in Metro Vancouver

Metro Vancouver, BC

Quick answer: Multigroup Contracting converted an approximately 3,000 sq ft empty commercial unit into a retail flooring showroom in Metro Vancouver. This tenant improvement included new walls, relocated accessible washrooms, laminate flooring, lighting and custom displays and counters. Retail buildouts · Tenant improvements · Commercial construction · Get a free quote

Project at a glance

Overview

A flooring store needed a showroom that would sell its product the moment customers walked in. The unit it had leased was a blank shell. We took the space from bare concrete to a bright, open, customer-ready showroom as one tenant improvement project, with one point of contact from start to finish.

Related services: Retail buildouts · Tenant improvements · Commercial construction

What was the challenge?

When we started, the unit had nothing a retail showroom needs. The floor was bare grey concrete. The beige walls had peeling and patched spots. The ceiling was open to an exposed steel roof deck with orange ductwork, and the lighting was a mix of dated hanging lamps and track lights. None of it showed product well.

The layout was the bigger problem. The washrooms were not where the new floor plan needed them, and moving washrooms in a commercial unit means moving drains that sit under the concrete slab. On top of that, the unit shared its building with other working businesses, so loud and dusty work like concrete coring could not simply run during the day.

The store also needed a space that worked as a sales tool: long sightlines, bright and even light, wall displays sized for flooring samples, and sales counters where staff could work with customers.

What did this retail showroom tenant improvement include?

We delivered the project as a complete retail showroom buildout. Here is what was included.

New walls and showroom layout

We built new walls and framed the showroom layout, separating the sales floor from the back area and setting up the space for displays, counters and the new washroom location.

Concrete slab coring and washroom relocation

To put the washrooms where the layout needed them, we completed about 80 feet of concrete slab coring, relocated the plumbing, then repoured the slab. All of this was done on night shift.

Two new accessible washrooms

We built two new accessible washrooms in the new location.

Luxury laminate flooring throughout

We installed luxury laminate flooring across the whole showroom. For a flooring retailer, the floor is part of the product display, so it had to be clean, flat and consistent from the entrance to the back wall.

Walls, ceiling, beams and ductwork painted white

We patched, primed and painted the walls. Overhead, we painted the ceiling, beams and ductwork white. This turned the dated orange-and-grey exposed ceiling into a clean, bright open ceiling that makes the space feel larger and helps the lighting do its job.

Showroom lighting

We installed new showroom lighting to replace the old hanging lamps and track lights, so customers can see colour and texture on the sample walls clearly.

Custom wall displays and sales counters

We custom built the wall displays and sales counters from scratch in plywood and laminate. The wall displays hold the store's flooring samples, and the counters give staff a place to work through options with customers.

Permits and trade coordination

We handled the permits for the project and closed them out, and we coordinated licensed subtrades, who worked under their own trade permits. The client dealt with one point of contact, not a list of separate trades.

How was the slab work done without disrupting neighbouring businesses?

We moved all concrete coring, plumbing relocation and slab repour work to the night shift, so the neighbouring businesses could operate normally during the day.

Concrete coring is loud and creates dust and vibration. In a building with other working tenants, doing that work during business hours would have disrupted the businesses next door.

The coring of about 80 feet of slab, the plumbing relocation underneath and the concrete repour were all done at night. By the time neighbouring businesses opened in the morning, the noisiest work had stopped. The rest of the buildout, including framing, washrooms, flooring, painting, lighting and millwork, followed in sequence so the project stayed on its one-month schedule.

For any business owner or landlord planning a tenant improvement in an occupied building, this is the practical lesson: plan the disruptive work around your neighbours from day one, not after the first complaint.

What were the results?

Before and after photos

Empty commercial unit before a retail showroom buildout, with bare concrete floor, worn beige walls and orange exposed ductwork
BEFORE — Before: empty unit with bare concrete, worn walls and orange ductwork
Custom plywood and laminate sales counters in a finished flooring showroom with white painted ceiling and new lighting
AFTER — After: custom sales counters and sample displays
Custom-built wall display holding flooring samples in a Metro Vancouver retail showroom
AFTER — After: custom-built flooring display walls
Long showroom aisle with luxury laminate flooring, white walls and white painted ductwork after a tenant improvement
AFTER — After: luxury laminate aisle and white painted ceiling

Frequently asked questions

Where was this retail showroom buildout?

The project was in Metro Vancouver, BC. The case study does not specify a municipality.

What was the starting condition and project type?

An empty commercial unit of about 3,000 sq ft was converted into a retail flooring showroom as a tenant improvement.

What custom displays and counters were built?

The project included wall displays and sales counters built in plywood and laminate for the retailer’s flooring samples.

What flooring and washroom work was included?

The documented scope included luxury laminate flooring across the showroom and two relocated accessible washrooms.

Related guides

Planning a showroom or retail buildout in Metro Vancouver?

Multigroup Contracting is a commercial general contractor serving Metro Vancouver since 2016. We are WorkSafeBC registered and carry $5 million in liability insurance. We build retail showrooms, store fit-outs and tenant improvements, from layout changes and washroom relocations to finishes, lighting and custom millwork. Call 778-819-5933 or contact us to talk about your space. CONTACT US