Power and data planning in an office tenant improvement comes down to three things that should all be settled before drywall closes: how much electrical capacity the new layout needs and where it comes from, how power and cabling will reach every desk, room and piece of equipment, and which landlord rules, permits and fire separation details apply on the way. After that, every missed outlet or cable path means opening finished work.

This guide is for office tenants, landlords and property managers planning a tenant improvement in Vancouver or elsewhere in Metro Vancouver. Electrical work is designed by an electrical engineer or designer and done by an electrical contractor, and data cabling by a low voltage specialist. The general contractor makes sure those pieces are planned, approved and built in the right order. For the bigger picture, see our guide to planning an office tenant improvement in Vancouver.

How much power does the new layout need, and where does it come from?

Start with an equipment and headcount list, not outlet symbols: workstations, printers, kitchen and coffee equipment, meeting room screens, the network rack and access control. Your electrical engineer or designer uses that list to work out loads and circuits. Then ask the landlord and building management early:

  • Which panel feeds the suite, and how much spare capacity and spare breaker space does it have?
  • Can existing circuits from the last tenant be reused, or do they need to be traced and labelled first?

The answers decide whether the job is a re-circuit of the existing panel or a larger electrical scope that changes the design, the landlord approval package and the permit drawings. If you are still comparing spaces, see our guide to empty shell vs second-generation office space.

Where should outlets, floor boxes and data drops go?

Outlets and data drops follow the furniture plan, so the furniture layout needs to be close to final before electrical and cabling drawings are issued.

  • Offices and meeting rooms: outlets and data in the walls, plus screens and video conferencing at the right height.
  • Open work areas: desks away from walls need power poles, floor boxes or furniture feeds, and each option affects the ceiling, the slab and the furniture order.
  • Kitchens and coffee areas: appliances often need their own circuits.
  • Reception and security: card readers, cameras and wireless access points need power and data too.

Floor boxes deserve extra care. Coring a concrete slab needs landlord approval, scanning the slab first helps avoid embedded services, and drilling concrete releases silica dust, which WorkSafeBC identifies as a serious lung hazard that needs dust controls. Floor boxes also have to line up with the new office flooring.

How do power and data reach each desk and room?

Pathways are the routes cables and conduit take: above the ceiling, inside partitions, through the floor and up the riser to the telecommunications room. Agree on them before framing starts.

  • Network room location: copper network cabling is designed around a 100 metre channel, made up of up to 90 metres of permanently installed cable plus patch cords, as the Fiber Optic Association explains. A network room placed at one end of a large floor can push far desks past that limit.
  • Plenum ceilings: in a building required to be of noncombustible construction, the BC Building Code allows voice and data cables with combustible jackets in a ceiling plenum only with the FT6 fire and smoke rating, unless they run in a totally enclosed noncombustible raceway. Whether the ceiling is a return air plenum is a question for the mechanical engineer and the landlord.
  • Partitions: boxes and conduit in new walls go in while the studs are open. See our guide to office partition layouts and permits.

What landlord rules apply to power and data?

Many office buildings have written building standards, and leases commonly require landlord approval of drawings before work starts. For power and data, check the rules on:

  • Access to electrical rooms, risers and the telecommunications room.
  • Required electrical and cabling trades, labelling and documentation.
  • Notice needed for power shutdowns, and when shutdowns and noisy work such as coring are allowed.
  • Slab coring, penetrations through floors and walls, and who inspects the firestopping.
  • Old cabling left by previous tenants, and what has to be removed at the end of your lease.

Make-good clauses can require removal of data and phone cabling at move-out, so ask now. Our guides to landlord approval for a commercial fit-out and lease make-good and restoration go into both.

Which permits and inspections apply in Vancouver and Metro Vancouver?

In Vancouver, renovating or improving a commercial space needs a building permit, as the City explains on its when you need a permit page. On top of that:

  • The City of Vancouver requires an electrical permit for almost all electrical work. Only a qualified electrical contractor with a valid business licence can apply, and if the project needs a building permit, the electrical permit is not issued until the building permit is.
  • Under the City's Tenant Improvement Program (TIPs) for eligible office buildings, trade permits follow the building permit and are typically submitted by the trade contractor hired by the general contractor. The City's minor renovation permit checklist notes that electrical professional plans may be required depending on scope.
  • Electrical work must meet the BC Electrical Code, whose 2024 edition (the Canadian Electrical Code, Part I, 26th Edition) took effect on March 4, 2025.
  • Outside Vancouver, Technical Safety BC lists Burnaby, Surrey, the City and District of North Vancouver and West Vancouver among the local governments that issue their own electrical permits. In Richmond, Technical Safety BC is the electrical permitting authority. See also our guide to commercial building permits in Burnaby.

Where Technical Safety BC issues the permit, a field safety representative declares that the work complies and requests inspection after each phase. Wherever you are, plan for the rough-in to be inspected before it is covered. If the fit-out changes fire alarm devices, flag it early: the City lists projects involving fire alarms among those not eligible for the TIPs stream.

How do you protect fire separations when cables pass through?

Corridor walls, demising walls, shafts and floors are often fire separations. The BC Building Code, which the Vancouver Building By-law is based on, generally requires ducts, outlet boxes, raceways and cables that pass through them to be sealed with a firestop tested to CAN/ULC-S115, with limited exceptions such as small noncombustible outlet boxes that meet size and gap limits. Outlet boxes on opposite sides of a rated wall also need to be offset by at least 600 mm, separated by a fire block, or protected by a tested firestop on each box.

Cabling is often added after the firestopping trade has finished. Agree on who seals every new penetration, use tested systems that match the assembly, and walk the separations before the ceiling closes. See our guides to fire and life safety in commercial renovations and acoustic planning, since the same gaps leak sound.

How does electrical work stay safe in an occupied building?

Tie-ins to an existing panel usually mean shutting circuits off. The BC Electrical Code requires electrical equipment to be de-energized before work, and Technical Safety BC states that inconvenience is not an acceptable reason to bypass that. WorkSafeBC requires low voltage equipment to be completely disconnected and locked out before work starts. Where other tenants stay open, shutdowns are booked with building management in advance, and noisy work like coring may need to happen outside business hours. See our guides to renovating a commercial building while it stays open and after-hours construction permits in Vancouver.

What should be on the checklist before drywall closes?

  • Final furniture layout and equipment list.
  • Electrical and cabling drawings coordinated with the architectural, ceiling and furniture plans (see our guide to office tenant improvement drawings).
  • Panel capacity confirmed with the landlord, and shutdowns scheduled.
  • Floor box and coring locations approved, scanned and matched to the flooring plan.
  • Network room, pathways and cable type confirmed, including FT6 cable in plenums.
  • Building permit issued, electrical permit in place, and rough-in inspected.
  • Every penetration of a fire separation sealed with a tested firestop and checked.
  • Spare conduit left where changes are likely, and circuits labelled.

How Multigroup Contracting helps

Multigroup Contracting is a commercial general contractor and fee-based construction manager with our Vancouver office at 700-838 West Hastings St. Founded in 2016, we are registered with WorkSafeBC and carry $5M in liability insurance. On an office fit-out, we bring the electrical contractor and the low voltage specialist into planning early, coordinate their drawings with your designer and the landlord's building standards, sequence permits, rough-in, inspections and firestopping so nothing is closed in too soon, and book shutdowns with building management. We build tenant improvements and office fit-outs in Vancouver and across Metro Vancouver.

Planning power and data for an office tenant improvement in Vancouver or Metro Vancouver? Get a free quote, call Multigroup Contracting at 778-819-5933 or email info@multigroup.ca.

FAQ

Who applies for the electrical permit on an office tenant improvement in Vancouver?

The electrical contractor. The City of Vancouver only accepts electrical permit applications from a qualified electrical contractor holding a valid City of Vancouver or inter-municipal business licence, and the electrical permit is not issued until the building permit for the project has been issued. The general contractor coordinates the timing so trade permits follow the building permit.

Do data cables in an office ceiling need a special fire rating?

Often, yes. In a building required to be of noncombustible construction, the BC Building Code allows voice and data cables with combustible jackets in a ceiling space used as a return air plenum only if they carry the FT6 fire and smoke rating, unless they run in a totally enclosed noncombustible raceway. Ask your designer early whether the ceiling is a plenum, so the right cable is specified and ordered.

Who issues electrical permits in Burnaby and Richmond?

It depends on the city. Technical Safety BC lists Burnaby among the local governments that issue their own electrical permits, along with Vancouver, Surrey and the North Shore municipalities. In Richmond, Technical Safety BC is the electrical permitting authority. Confirm the right office before the electrical contractor applies.

Why does firestopping matter for power and data work?

Every outlet box, conduit, cable bundle or tray that passes through a fire separation opens a gap in that separation. The BC Building Code generally requires those penetrations to be sealed with a firestop tested to CAN/ULC-S115, and the City of Vancouver's minor renovation permit checklist asks for firestopping details for service penetrations of fire separations. It is far easier to get right before the walls and ceiling close.

Can the electrical tie-in be done while the building stays powered?

Usually the circuits being worked on have to be shut off. The BC Electrical Code requires electrical equipment to be de-energized before work, and Technical Safety BC states that inconvenience is not an acceptable reason to work on live equipment. WorkSafeBC also requires low voltage equipment to be disconnected and locked out before work starts. Plan shutdowns with the landlord and building management ahead of time.